US20070112451A1 - Glass demand scheduling system - Google Patents

Glass demand scheduling system Download PDF

Info

Publication number
US20070112451A1
US20070112451A1 US11/652,747 US65274707A US2007112451A1 US 20070112451 A1 US20070112451 A1 US 20070112451A1 US 65274707 A US65274707 A US 65274707A US 2007112451 A1 US2007112451 A1 US 2007112451A1
Authority
US
United States
Prior art keywords
production
insulating glass
glass units
fabrication
schedules
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US11/652,747
Inventor
Byron Clayton
Paul Dorsch
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GED Integrated Solutions Inc
Original Assignee
GED Integrated Solutions Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GED Integrated Solutions Inc filed Critical GED Integrated Solutions Inc
Priority to US11/652,747 priority Critical patent/US20070112451A1/en
Assigned to GED INTEGRATED SOLUTIONS, INC. reassignment GED INTEGRATED SOLUTIONS, INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: CLAYTON, BYRON, DORSCH, PAUL
Publication of US20070112451A1 publication Critical patent/US20070112451A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B33/00Severing cooled glass
    • C03B33/02Cutting or splitting sheet glass or ribbons; Apparatus or machines therefor
    • C03B33/023Cutting or splitting sheet glass or ribbons; Apparatus or machines therefor the sheet or ribbon being in a horizontal position
    • C03B33/037Controlling or regulating
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32252Scheduling production, machining, job shop
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/45Nc applications
    • G05B2219/45174Making panels
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/49Nc machine tool, till multiple
    • G05B2219/49366Machine several small pieces on one sheet, break off pieces
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/50Glass production, e.g. reusing waste heat during processing or shaping
    • Y02P40/57Improving the yield, e-g- reduction of reject rates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/40Minimising material used in manufacturing processes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Definitions

  • the present invention concerns a method and apparatus for controlling production run sequences of insulating glass units.
  • Window manufacturers typically receive orders that include a variety of different sizes and types of windows and/or patio doors.
  • the different sizes and types of windows and/or patio doors require different sizes and types of insulating glass units (IGs) that are assembled into a frame or sash to form a completed window or patio door at one or more glazing lines.
  • IGs insulating glass units
  • the window manufacturers separate and group the orders for the IGs into regular or planned production runs.
  • the regular or planned production runs are scheduled to be manufactured in a certain sequence on a certain future date, usually within one to three business days ahead.
  • Variables in the manufacturing process rarely allow the regular production runs to be manufactured in the exact planned sequence. For example, rush orders for important customers and remake orders that occur when IGs break are often prioritized, changing the sequence of the production runs.
  • the operational status of machines used to make the components of the IGs may also cause the sequence of the regular or planned production runs to be altered.
  • demand fluctuations, such as a shortage at one of the glazing lines may cause the sequence of the regular or planned production runs to be altered.
  • a supervisor of an IG production line must constantly monitor each of the manufacturing variables and modify the sequence of the production runs accordingly.
  • the glass lites that are needed to construct the IGs are separated and grouped into scheduled production batches or runs. For each production batch, the glass lites are further grouped and arranged to be cut from large stock glass sheets to achieve the highest yield. The process of grouping and arranging glass lites to be cut from stock glass sheets to achieve the highest yield is called glass optimization.
  • Glass optimization is usually performed by a computer executing a computer program.
  • the output from the glass optimization process is a control program that is sent to a computer-controlled cutting table.
  • the glass optimization software outputs a computer program that optimizes one or more production batches containing patterns of lites arranged on stock glass sheets.
  • the cutting table automatically scores the glass according to each pattern.
  • Each production batch normally contains one or more glass layout patterns that provide a lower yield than desirable.
  • the claimed invention is a method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation.
  • the method comprises compiling a plurality of orders and converting the plurality of orders into production schedules for operating a plurality of processes that fabricate the insulating glass units over a prescribed period of time.
  • the method further includes releasing the production schedules to the plurality of processes used to fabricate insulating glass units.
  • the production schedules are accessible to users through a computer network.
  • the method also includes monitoring production operations data produced as a result of the releasing the production schedules to the plurality of processes used to fabricate the insulating glass units and providing reports used by the monitoring production operations having image readable indicia that are imaged for providing real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units.
  • the claimed invention includes computer-readable media having computer-executable instructions for performing a method optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation, the instructions comprising the step of producing a plurality of production schedules for equipment and assembly operations used to fabricate windows and window components over a prescribed period of time.
  • the instructions further comprise releasing the production schedules to the equipment and assembly operations used to fabricate window and window components.
  • the production schedules are accessible to users through a computer network.
  • the instructions also comprise calculating production operations data associated with the productions schedules. The calculating of the production operations includes using information from continuous real-time data collected from tracking material and components through the equipment and assembly operations used to fabricate window and window components.
  • the claimed invention is a method for controlling production schedules of insulating glass units, components, and materials in equipment and assembly operations comprising the steps of compiling a plurality of new, remake, and rush orders used to fabricate insulating glass units and converting the plurality of orders into production schedules for operating a plurality of equipment and assembly operations that fabricate the insulating glass units over a prescribed period of time.
  • the method further includes releasing the production schedules to the plurality of equipment and assembly operations that fabricate insulating glass units, the production schedules being accessible to operators and management through a computer network and monitoring production operations data produced as a result of the releasing the production schedules to the plurality of equipment and assembly operations and real-time feedback information.
  • the monitoring production operations data includes: monitoring individual machine production rates used to fabricate the insulating glass units; monitoring individual machine completion rates used to fabricate the insulating glass units; monitoring individual kanban arrival times having a known amount of material used to fabricate the insulating glass units; monitoring individual kanban consumption rates of the known amount of material used to fabricate the insulating glass units; and monitoring individual machine start times used to fabricate the insulating glass units.
  • the method further includes the steps of alerting operators and/or management should the materials supplied to one or more of the plurality of equipment or assembly operations fall below a prescribed material queue threshold, creating a material notice condition based on the monitoring production operations data and altering one or more of the production schedules based on the material notice condition.
  • FIG. 1 is a schematic representation of a window and/or door manufacturing facility
  • FIG. 2 is a schematic representation of a window and/or door manufacturing facility equipped with a system for controlling production run sequences of insulating glass units;
  • FIG. 3 is a schematic representation of a user interface by means of which an operator controls production run sequences
  • FIG. 4 is a schematic representation of a user interface by means of which an operator controls production run sequences
  • FIG. 5 is a schematic representation of a user interface by means of which an operator controls production run sequences
  • FIG. 6 is a flow chart that illustrates one method of controlling production run sequences
  • FIG. 7 is a schematic representation of a cutting station located within a window or door manufacturing facility
  • FIG. 8 is a schematic of a user interface by means of which an operator sets up cutting operations at the FIG. 1 cutting station;
  • FIGS. 9-15 are schematic depictions of glass sheets illustrating layouts of lites to be cut from the sheets at the cutting station
  • FIGS. 16A and 16B are flowcharts for optimizing lite layouts on glass sheets of a production run
  • FIGS. 17A and 17B are flowcharts illustrating a process for managing and optimizing material flow and equipment utilization through the production process of FIG. 2 in accordance with the present invention.
  • FIG. 18 illustrates a printing operation for a plurality of reports for providing information to the production process of FIG. 2 in accordance with the present invention.
  • the disclosed invention provides an integrated software and apparatus solution used in the manufacture of windows and/or doors for dynamically monitoring manufacturing variables and controlling production sequences using central production control workstation 10 ( FIG. 2 ).
  • FIG. 1 schematically illustrates a window and/or door manufacturing facility 12 .
  • the facility 12 includes a front end system or terminal 14 where orders for windows and/or doors are entered and window assembly is scheduled.
  • the front end system 14 provides orders 16 to an insulating glass unit (IG) production control terminal 18 .
  • the orders 16 may include regular production orders 20 , rush orders 22 , and remake orders 24 .
  • the rush orders 22 are orders that are prioritized, usually due to a customer demand.
  • the remake orders 24 are entered when an IG 25 , a component of an IG, or a finished window or door 58 is damaged.
  • remake orders are provided directly to the central control workstation 18 by an electronic communication 19 from a glazing line or a window component processing station ( FIG. 2 ).
  • the regular production orders 20 are orders that have not been tagged as a rush order or a re-make order.
  • the production control terminal 18 receives the orders 16 as input and creates a sequence of runs of insulating glass units to be produced at an insulating glass unit (IG) department 26 .
  • the IG department includes several insulating glass component processing machines or stations that construct IG components and assemble the IG components to create IGs.
  • the IG component processing stations include a glass cutting station 28 , a spacer frame production station 30 , a muntin bar production station 32 , a muntin bar assembly station 34 , a glass washing station 36 , an IG assembly station 38 , an oven 40 , a gas fill station 42 , and a patching station 44 .
  • Glass lites 46 , spacer frames 48 , and muntin bars 50 are constructed at the glass cutting station 28 , the spacer frame production station 30 , and the muntin bar production station respectively.
  • the glass lites, spacer frames, and muntin bar grids 50 are assembled to form IGs at the IG assembly station 38 .
  • the IGs are fed through the oven/press 40 , which presses the IG to a predetermined thickness and heats the adhesive/sealant that secures the lites to the spacer frame.
  • the IGs are then filled with an inert gas at the gas fill station 42 and patched at the patching station 44 .
  • An IG department supervisor 45 is responsible for managing each of the IG component processing stations to ensure that demands for IGs by a glazing department 60 are met.
  • glazing is to be interpreted as installing a glass lite or IG in any window or door component and the term sash is to be interpreted as any window or door component that surrounds a glass lite.
  • the finished IGs are placed on carts 54 in a staging area 56 .
  • the carts 54 in the staging area 56 form a visual kanban system 55 , providing production personnel with a visual signaling system by monitoring the number of carts in the staging area assigned to an assembly line in a glazing department 60 .
  • the IGs are taken from the carts 54 and are assembled with window sash and frames or doors in the glazing department 60 to construct completed windows and/or doors 58 . Assembly of an IG to a window or door sash and/or a frame is broadly referred to herein as glazing.
  • the glazing department 60 includes several discrete glazing lines 62 .
  • FIG. 2 illustrates a window and/or door manufacturing facility 12 equipped with a system 64 for controlling production run sequences of insulating glass units.
  • the production control terminal 18 receives orders electronically as indicated by arrow 66 from the front end system 14 .
  • the control terminal 18 electronically sends and receives information to and from the glass component processing machines as indicated by arrow 68 .
  • the front end system 14 and the control terminal 18 receive demand information electronically from the glazing lines as indicated by arrows 70 , 72 respectively. This information includes a number of runs 74 in a queue 76 for each glazing line.
  • the control terminal 18 also receives remake requirement information from the glazing lines as indicated by arrow 78 . Additional remake information may be provided from one or more of the stations in the IG department.
  • the production control terminal 18 is a controller or ancillary computer including a programmable device in communication with a programmable device 80 located at each window component processing station and a programmable device 82 located at the plurality of glazing lines.
  • programmable devices 80 are electrically coupled to controllers of window component processing stations that include compatible machine controllers. This allows the sequence of these window processing stations to be altered automatically. Compatible machines automatically run the next production run in the sequence, if configured for Auto Sequencing.
  • window component processing stations include the glass cutting station 28 , the spacer frame production station 30 , the muntin bar production station 32 , and the oven 40 , in the exemplary embodiment.
  • Non-compatible machines utilize the satellite programmable devices 80 to alert the operator of the new production run sequence.
  • Such stations may include a muntin bar assembly station 34 , the glass washing station 36 , an IG assembly station 38 , a gas fill station 42 , and a patching station 44 .
  • the status of the runs of IGs, the status of the insulating glass component processing machines, and the queue of insulating glass units to be assembled at each glazing line can be viewed at the production control terminal 18 or workstation.
  • the screen illustrated by FIG. 3 provides the IG supervisor with the status of complete IG production runs, the status of runs of IG components, and the status of completed IG runs in queue at the glazing lines.
  • Column 400 provides the IG supervisor with the overall status of IG production runs.
  • Column 402 provides the IG supervisor with the status of runs of muntin bars that correspond to each overall IG production run.
  • Column 404 provides the IG supervisor with the status of runs of glass lites that correspond to each overall IG production run.
  • Column 406 provides the IG supervisor with the status of runs of spacer frames that correspond to each overall IG production run.
  • Column 408 provides the IG supervisor with the status of the IG runs of at the gas fill and patching station.
  • Column 410 provides the IG supervisor with the glazing line number or description and the status of each completed IG production run at the identified glazing line.
  • the screen of FIG. 4 provides the IG supervisor with the status of the completed IG runs in the glazing queue of each glazing line.
  • columns 412 , 414 , 416 , 418 provide the status of each run 420 of assembled IGs in the queues 422 of glazing lines 1 , 2 , 3 , and 4 respectively.
  • the stiphing and cross-hatching of FIG. 4 corresponds to the legend shown in FIG. 3 .
  • the screen illustrated by FIG. 5 provides the IG supervisor with the status of each production run 424 in the production run queue for each window component processing station.
  • Column 428 provides the status of the muntin runs.
  • Column 430 provides the status of the glass cutting runs.
  • Column 432 provides the status of the spacer frame runs.
  • Column 434 provides the status of the IGs at the gas fill and patch station.
  • the IG supervisor alters the sequence of runs based on one of the status of the runs, the status of one or more of the glass processing machines, and the queue of insulating glass units at the glazing line at the production control terminal.
  • the following manufacturing variables can all be monitored at the production control terminal 18 :
  • production run sequences are downloaded 86 from the terminal 14 to the control terminal 18 .
  • Software running on the control terminal 18 determines 88 whether the runs received from the customer terminal 14 are larger than a user defined Run Size Parameter. If the number of IG units per production run surpass the number of IG units specified in the Production Run Size Parameter, the method automatically divides or segments 90 the runs into segments based on the size parameter setting.
  • the Production Run Size Parameter is entered by a user via a setup menu. Some customers create one or more very large daily production runs. For those customers, the system automatically segments large runs from the terminal 14 into a number of smaller runs, identifying each as some subset of the whole. Small production runs, typically matching the IG cart size, provide the flexibility required to properly level-load the glazing lines.
  • the IG supervisor may view 92 the IG Department Queue at the Central Workstation 18 (see FIG. 3 ). This view provides the supervisor with an accurate snapshot of the status of all scheduled IG production runs via color codes (These codes are designated by cross-hatching and stiphing different patterns in the Figures).
  • the supervisor can view the production run status 94 of each of the machines, the overall production run status and requests to prioritize a particular run 96 from satellite devices 80 , 82 , and low queue conditions 98 from the glazing lines.
  • a low queue condition at a glazing line may be automatically detected or entered through a satellite device by a glazing line worker.
  • the supervisor uses the information on the display to determine 100 whether the current production sequence maintains an efficient, uninterrupted production flow through the IG Department.
  • the IG supervisor changes 102 the production control sequence at the control workstation 18 .
  • the determination 100 of whether action needs to be taken and the run sequence changed 102 is performed by the software in the control terminal 18 .
  • Each status or sequence changed at the central control terminal 18 is updated 104 automatically and provided 106 to all of IG component processing stations and the glazing lines by compatible machine software and/or the satellite programmable devices 80 , 82 .
  • a change of the production run sequence at the central workstation immediately changes the corresponding sequences in a database maintained at the workstation 18 and display of compatible machine controllers and satellite programmable devices.
  • Compatible machines automatically run 110 the next production run in the sequence, if configured for auto sequencing.
  • Non-compatible machines utilize satellite programmable devices to alert the operator of the new production run sequence.
  • required labels and reports are automatically printed 112 for each production run using a compatible printer.
  • a parameter in the setup menu determines how far in advance to print labels and reports for each production run.
  • the IG supervisor may manually print selected reports via a user-friendly menu.
  • the labels and reports will accompany the IG through the manufacturing process.
  • an operator may use the graphical display to print and/or display 114 labels, reports, and/or low queue condition statistics.
  • a partially completed production run has either been started at the machine or is reserved using a Production Run Look-Ahead Parameter. This parameter reserves a specific number of the next available production runs for glass optimization purposes or to give the IG supervisor sufficient time to print and deliver labels and reports to the production floor.
  • the Production Run Look-Ahead Parameter is entered via a setup menu.
  • the system may allow the IG supervisor to display the glazing line queue (see FIG. 4 ).
  • the supervisor uses this display to monitor the level-loading of each glazing line and changes the run sequence as needed to prevent low queue conditions at a given glazing line.
  • the system includes a glazing line monitoring system.
  • the system automatically monitors each glazing line queue 422 for a “low queue condition.” This condition is met when the production runs 104 waiting to be glazed fall below a parameter set for each glazing line 62 in the setup menu.
  • the low queue condition is automatically detected by identifying runs of assembled insulating glass units that are delivered to each glazing line and identifying runs of assembled insulating glass units that are assembled to windows, or otherwise processed at each glazing line.
  • this identifying of runs of IGs that enter and exit the glazing lines is performed by scanning an identification label.
  • the system automatically highlights the next available production run for that glazing line in red at the central workstation 18 . This highlighting alerts the IG supervisor that he should change the sequence to prevent shutting down the glazing line.
  • glazing line personnel may also use satellite programmable devices 82 located at each glazing line to force a “low queue condition”. This feature allows the glazing line personnel to request the next available production run for that glazing line from the IG Department at the terminal 18 . Glazing line personnel may also use satellite programmable devices to prioritize specific regular, rush or remake production runs. The request alerts the IG supervisor by highlighting the corresponding production run on the display of the central workstation 18 .
  • the invention allows the IG supervisor to react to manufacturing variables by modifying the sequence of the production runs using a graphical drag and drop function.
  • the software uses the input from the drag and drop function to create a new or altered production run sequence. Once the software has completed creating the new production run sequence, the system automatically performs the following tasks:
  • the system includes three software tools that help manage each glazing line queue.
  • the first tool provides a parameter in the setup menu to dictate the minimum number of production runs staged for each glazing line.
  • the system uses this parameter to automatically alert the IG supervisor of a “low queue condition” by highlighting the next available production run for that glazing line in red when the number of production runs in queue falls below the set minimum number. The IG supervisor will then make the decision to change the priority of that production run.
  • the second tool provides statistics describing the number of “low queue conditions” for each glazing line over time. This provides the IG supervisor with information to increase or reduce the size of the queue limit for each glazing line These tools help the IG supervisor optimize the size of the glazing line queues to achieve the highest throughput.
  • the third tool allows glazing line personnel to use a satellite programmable device 82 to force a “low queue condition” or to prioritize a specific regular, rush or remake production run for a particular glazing line.
  • the request alerts the IG supervisor by highlighting the corresponding production run on the display of the central workstation.
  • the disclosed system provides the IG supervisor with real-time, accurate and simple tools to monitor manufacturing variables and control production run sequences.
  • the supervisor will easily accomplish existing tasks in a fraction of the time, using accurate real-time data.
  • Production run sequences will be set in plenty of time to continue standard manufacturing procedures without any loss of production efficiency.
  • One component of the disclosed system is a glass optimization module for increasing the yield of glass cutting runs during window or door manufacture, or other manufacture requiring glass lites.
  • An exemplary glass optimization module or program automatically recognizes and optimizes Low Yield Sheets by adding glass lites from other production batches as well as lites entered or selected at the cutting station 28 .
  • the exemplary glass optimization module also automatically creates, tracks, selects and re-cuts remnant sheets of glass if the process is unable to add sufficient lites to eliminate Low Yield Sheets from a production batch.
  • the FIG. 7 cutting station 28 includes a controller 212 that provides the cutting station operator an option of easily selecting filler lite sizes that can be automatically inserted into each production batch.
  • the controller is coupled to a display or breakout monitor 214 that graphically alerts the cutting table operator(s) which cart and slot to place each lite as it is cut.
  • the controller 212 and breakout monitor 214 also graphically alert the cutting table operator(s) where to place or remove remnant sheets for subsequent processing.
  • the controller and breakout monitor also graphically alert the cutting table operator(s) which temporary cart slot to place or remove lites for subsequent processing.
  • the system tracks and reports yield, throughput and filler lite information in real-time to the cutting table display or monitor 214 as well as other computers by means of a network 216 which allows the controller 212 to communicate with other computers in the manufacturing facility, including the central control terminal 18 .
  • These other computers include computer-controlled manufacturing devices at other workstations and computer software for controlling the entire manufacturing process.
  • FIG. 7 depicts representative apparatus for optimizing the fabrication of products that include lites cut from the glass sheets.
  • the cutting station 28 including a moveable cutting head 220 supported for movement with respect to a glass sheet 222 ( FIG. 9 ) positioned on a cutting table 224 with respect to the cutting head 220 from which glass lites are cut.
  • the same controller 212 that updates the display or monitor 214 is also responsible for controlling the movement with respect to the cutting table of the cutting head 220 .
  • FIG. 9 shows a representative sheet 222 having a number of lites 230 - 233 scheduled to be cut from specified locations on the sheet 222 .
  • Typical dimensions (prior to cutting) for a sheet such as the sheet 222 shown in FIG. 9 are 72 inches by 84 inches.
  • Other standard sizes are 96′′ by 130′′ and 48′′ by 60′′.
  • the sheet 222 is removed by an operator from one of two racks 240 , 241 ( FIG. 7 ) positioned in relation to the cutting table 224 .
  • the sheet is placed on its edge at the side or at the end of a free fall table 242 .
  • the table 242 has a relatively smooth and soft top surface onto which the glass sheet falls. From its position on the table the sheet is automatically transferred to the cutting table 224 . While on the cutting table 224 the sheet 222 is cut by the cutting head and then moved to a break out table 244 . At the break out table 244 an operator breaks out the lites from the glass sheet 222 .
  • a number of carts 250 - 253 are positioned with respect to the cutting station 28 for storing lites as they are cut from a glass sheet 222 by the cutting head 220 .
  • the controller 212 or another ancillary computer includes software running on a processor, which performs a number of tasks used by the system for making the glass cutting process more efficient.
  • the controller lists a number of batches wherein each batch requires a specified number and type of glass lites for use in fabricating products in an associated job.
  • the controller 212 (or ancillary computer) and breakout monitor 214 displays a pattern of lites to be cut from a first set of glass sheets to fulfill the lite requirements for one batch and during cutting prompts the operator to place the lites for that job into a single one of the four carts 250 - 253 .
  • under utilized glass sheet is any sheet where less than 70% of the sheet has lites allocated for a given job.
  • the sheet 222 depicted in FIG. 9 is an underutilized glass sheet having free space 260 with no lites designated to be cut for the batch that the sheet 222 is associated with.
  • the four lites 230 that have been designated for a particular batch have been labeled with the designation “P” to indicate that they are associated with a particular production batch. These four lites 230 - 233 take up much less than the 70% cutoff.
  • the controller 212 or ancillary computer responds to recognition of such an underutilized sheet by laying out a pattern of lites to be cut to fulfill other lite requirements, possibly the other requirements one or more additional batches in a queue of such batches.
  • the controller utilizes at least some of the free space 260 on the underutilized glass sheets of a first batch by designating usage of the free space 260 for other batches.
  • the controller 212 or ancillary computer then completes the designated lites for those other or subsequent batches by laying out other glass sheets from which to cut other lites in that subsequent batch(es). This process, of course, takes into account the lites that have already been designated from the underutilized sheet or sheets of the previous batch or batches.
  • the software running on the controller or ancillary computer of the cutting station begins heuristically optimizing a next production batch in a queue of such batches by identifying a Low Yield Sheet if it exists.
  • the controller or ancillary computer automatically calculates how to fill the sheet according to a list of priorities exemplified by the flowchart 310 in FIGS. 16A and 16B .
  • FIGS. 9-15 the glass lites are labeled with designators depending on where in the list of priorities these lites are identified for inclusion onto a Low Yield Sheet.
  • the highest priority is a regular production batch lite P.
  • a next highest priority is a local remake or MDI lite L.
  • Three such lites 31 are depicted in FIG. 4 .
  • An MDI lite is typically made in response to a request due to breakage or a prior knowledge of a need by the cutting station operator. MDI lite information is entered by the operator at controller 212 using a keypad. A local remake is typically required because a lite is broken at the cutting table. Local remake information is entered by the operator using pushbuttons to highlight the lite that needs to be replaced on the breakout monitor or on the controller display.
  • a next highest priority lite inserted into the Low Yield Sheet is a production run look ahead lite LA.
  • Two such lites 232 are depicted in FIG. 11 .
  • a typical manufacturing sequence of batches will have need for lites from the same type of glass in multiple batches. The system recognizes this need by inserting lites for subsequent batches on a Low Yield Sheet. These are called look ahead lites LA because the system “looks ahead” to subsequent jobs for lites to add to a Low Yield Sheet.
  • the viewing monitor 214 tells the operator where he or she should put that look ahead lite. This is typically in the form of a cart slot number at the cutting station.
  • the next priority lite added to a Low Yield Sheet is a filler lite F.
  • Filler lites are certain sizes and glass types that are commonly used in production.
  • the system adds filler lites to Low Yield Sheets to increase yield. They are stored in close proximity to the cutting table.
  • the number of filler lites needed is noted on the display. (See FIG. 16 ) As the number of filler lites that have been cut increases, the corresponding number of filler lites that are needed decreases and the video display will be updated until the desired number of filler lites has been cut.
  • an appropriate filler lite can be quickly retrieved from the storage area.
  • FIGS. 9-15 suggest that the controller places lites of a similar nature together on the glass sheet, the controller may rearrange the lites on a pattern to increase yield and may for example intersperse lites of different types next each other on the glass sheet.
  • a temporary lite T is designated as a lite to be stored in a temporary cart until a cart for it's production batch has been placed at the cutting table in the positions illustrated in FIG. 7 by carts 250 , 251 , 252 , or 253 .
  • a remnant is designated as the remaining area of the large stock glass sheet that can be stored and used later in the optimization process.
  • the invention will instruct the cutting table if and how to cut the remnant for easier storage and store the position and size information of the remnant for subsequent optimization.
  • the controller optimizes glass usage to reduce waste during glass cutting utilizing the sequence of priorities.
  • the invention may also heuristically change the sequence of priorities based on input gathered via a computer network from other machines or programmable devices.
  • the cutting table operator presses 312 a function key on the controller.
  • the controller responds by displaying 314 a graphical display 270 similar to FIG. 8 .
  • a Production Run Look-Ahead Parameter 272 Listed on the display 270 is a Production Run Look-Ahead Parameter 272 .
  • This parameter corresponds to how many production batches the controller will look-ahead for lites to increase the yield on Low Yield Sheets.
  • the yield (as a percentage) that the controller uses to determine a Low Yield Sheet is entered during the initial setup of the invention.
  • Each production run typically corresponds to one cart. Therefore, if the Production Run Look-Ahead parameter displays the number ‘ 3 ’, the operator knows to place 316 three carts 250 , 251 , 252 around the cutting table.
  • the display 270 ( FIG. 8 ) also includes a Temporary Cart Look-Ahead Parameter 274 . If a number other than 0 is displayed, the operator places 318 a temporary cart or carts (cart 253 for example) at the cutting table. The displayed parameter indicates the number of additional production runs (in addition to the production run look ahead) to be checked with the look-ahead function. Assuming the temporary cart look ahead is other than zero, the Breakout Monitor will display which slot in the temporary cart the operator should place the lites identified from those production batches. In a typical application there is only one temporary cart for storing lites from multiple additional batches. When those additional batches are cut, the operator is prompted to move an already cut lite from its slot in the temporary cart and moved to its appropriate (and now in place) production run cart location or slot.
  • the operator views the Filler Lites Needed table 276 and enters the desired number of filler lites. Whenever possible, the invention adds the sizes of filler requested to Low Yield Sheet until the requested amount of filler lites is satisfied.
  • the operator views the Auto Sequencing Parameter. If “off”, the operator cannot change the order of the production batches in the queue. The order of the production batches will be determined by external software. If “on”, the operator may rearrange 322 the order of any production batches not started. Color coding of the display of FIG. 2 indicates which production batches in a list 280 are not started.
  • the cutting table will begin the next production run in the queue.
  • the invention automatically identifies Low Yield Sheets and will calculate how to get the best yield.
  • the sequence of steps 330 depicted in FIG. 16B inform the operator which type of sheet to drop on the cutting table.
  • the invention will follow a user-defined sequence of priorities to determine how to increase the yield by adding lites to the Low Yield Sheet from different sources.
  • the invention adds lites from MDI (manual data input), local remake entry, future production runs and standard sizes (filler lites).
  • the invention may also heuristically change the sequence of priorities based on input gathered via a computer network from other machines or programmable devices.
  • the invention will determine if the lites on the low yield sheet can more efficiently fit on a stored remnant sheet in a manner that eliminates the low yield condition. If so, the controller and breakout monitor alert the operator to load the corresponding stored remnant sheet from a remnant storage and retrieval system 45 having a cart for storing remnant sheets. The size and configuration of the Remnant Sheet Queue will be entered during the initial setup of the invention.
  • the system scores the largest rectangle possible in the unused area of the Low Yield Pattern.
  • the breakout monitor alerts the operator to transfer the remnant sheet to a manual, semi-automatic or automatic remnant storage and retrieval system 245 .
  • the breakout monitor also indicates which cart and slot (standard or temporary cart) to place each lite via text and color coding.
  • the invention also tracks and reports yield, throughput and filler lite information in real-time to the cutting table display as well as other computers, computer-controlled devices and computer software.
  • FIGS. 17A and 17B are flowcharts illustrating a process for managing and optimizing material flow and equipment utilization through a production process in accordance with the present invention.
  • FIGS. 17A and 17B illustrate a glass demand system 500 that includes software 510 or other forms of computer readable media used to efficiently manage the material flow through the production process as illustrated in FIG. 2 .
  • the software 510 is loaded onto the computer network 216 , which would include all computer terminals related to the production operation, such as the central workstation 18 , satellite devices 80 , and programmable devices 82 .
  • the software 510 is executed in the network 216 at 512 .
  • the software 510 supports user created merge files 514 comprising regular production orders 20 , rush orders 22 and remake orders 24 .
  • the merge files 514 are structured to conveniently allow for frequent changes and/or creation of new merge files for each day or shift of production as depicted at 516 .
  • the software 510 converts the merge files into machine readable programs or machine schedules 524 at 520 .
  • the machine schedules 524 are then placed into a demand pre-release folder 518 at 522 .
  • the demand pre-release folder 518 containing the machine schedules 524 are now readily accessible by a supervisor and/or operator via the software 510 at 526 linked to the computer network 216 .
  • the supervisor and/or operator can evaluate whether the machine schedules 524 are satisfactory or require modification.
  • the machine schedules 524 would be modified before the start of a shift, however, it would not depart from the spirit and scope of the claimed invention to enable the supervisor and/or operator to modify the machine schedules after a shift has started or during production run.
  • the supervisor and/or operator will resequence or reassign (to alternate machines or kanbans) the machine schedules 524 to modified schedules 530 at 532 .
  • Several factors in the production operation could render the machine schedules 524 unsatisfactory requiring resequencing or reassignment 532 .
  • changes in production orders 16 including regular production orders 20 and/or rush orders 22 and/or remake orders 24 could influence such required changes
  • low queue 76 signals or indications in the IG runs 74 for particular glazing lines 62 could provoke a change, or machine breakdown in the IG department 26 or glazing department 60 .
  • the resequencing or reassignment 532 by the supervisor or operator can be achieved at any network 216 terminal by a similar “drag and drop” application in the software 510 , as previously discussed.
  • the resequencing or reassignment 532 may change the order or amount of materials being processed at any individual line or machine within the IG department 26 . This could include for example, changes to the assembly operation 38 , cutting station 28 , or oven 40 in the IG department 26 . Similarly, changes may occur at the glazing lines 62 as a result of the resequencing or reassignment process 532 .
  • the modified schedules 530 or satisfactory machine schedules 524 mature into final schedules 534 and are released to the machines, equipment, IG lines located within the IG department 26 or computer workstations on computer network 216 at 536 .
  • the software 510 then calculates operations data 538 based on the final schedules 534 and the sequences are released to the equipment and assembly lines.
  • the software 510 further uses the calculated operations data 538 to perform several different computations relating to the production operations shown in FIG. 2 , including:
  • the calculated operations data 538 relating to the various operations described above, are monitored at 542 to help prevent future Out-of-Glass conditions 544 that could arise. For example, if the kanban 55 staging area 56 has only one hour of glass left in a particular glazing line 62 based on the KCR and the next cart 54 with IG units is scheduled to arrived at the kanban 55 in two hours an Out-of-Glass condition 544 is detected and the software 510 will issue an Out-of-Glass Alert 550 , indicating and notifying production personnel when the kanban staging area 56 will run out of glass. In one embodiment, the software 510 will calculate which schedule or schedules 524 will be advanced 552 in the production sequence upon issuing the alert 550 .
  • the software 510 in anticipation of the alert 550 will calculate which schedule or schedules 524 will be advanced in the production sequence and may be automatically advanced at 556 by the software 510 .
  • the operator or supervisor manually elects at 558 which schedule or schedules 524 will be advanced in the production sequence as a result of the calculation 552 provided by the software 510 or based on the supervisor/operator's own independent decision or instruction by another person or source.
  • the software 510 additionally supports a printing operation 600 that provides a number of reports that are used by both production personnel and management.
  • the reports assist in providing real-time information 539 to the production operations data 538 via manual and automatic scanning of material throughput (discussed further below) during the manufacturing process.
  • the print operation 600 produces an IG Cart Report 610 for schedules 524 having at least one cut glass lite.
  • the IG Cart Report is printed typically near the cutting glass station 28 when the schedule starts to assist production personnel in tracking the schedules 528 through the production operation.
  • the print operation 600 also produces an IG Cart Office Report 620 for schedules 528 with all purchased glass.
  • the IG Cart Office Report 620 is typically printed in a manager's office 625 when the schedule is released to the cutting glass station 28 for assisting management personnel in tracking the schedules 528 through the production operation.
  • the print operation 600 also produces a Purchased Glass Report 630 for schedules 528 with at least one purchased glass lite.
  • the Purchased Glass Report 630 is typically printed near the cutting glass station 28 when the schedule 528 starts.
  • the Purchased Glass Report 630 assists production personnel in tracking the glass used by the various schedules 528 .
  • the print operation 600 also provides a Purchased Glass Office Report 640 for schedules 528 with all purchased glass.
  • the Purchased Glass Office Report 640 is typically printed in the manager's office 625 when the schedule is released to the cutting glass station 28 for assisting management personnel in tracking the schedules 528 through the production operation.
  • the print operation 600 also provides a Production Muntin Report 650 .
  • the Production Muntin Report 650 typically prints near the muntin bar station 32 .
  • the Production Muntin Report 650 assists production and management personnel in tracking the raw materials used in forming the muntin bars.
  • the print operation 600 also provides a Production IG Report 660 .
  • the Production IG Report 660 typically prints near the spacer frame production station 30 .
  • the Production IG Report 660 assists production and management personnel in tracking the raw materials being used to make the IG assemblies in the spacer frame production stations 30 .
  • the print operation 600 also provides a Glass Label Report 670 consisting of one or more individual glass labels.
  • the Glass Label Report 670 typically prints near the spacer frame production station 30 .
  • the Glass Label Report 670 assists production and management personnel in tracking the IG assemblies as they are routed through the production operation.
  • the above reports can also be used to assist in the accuracy of the calculated operations data 538 by providing real-time data.
  • a patch operator assigned to the patch station 44 will scan data (using either a stationary or portable scanner device) such as a bar code relating to the IG assemblies on the Production IG Report 660 or glass label 670 as it leaves the patching station 44 .
  • the content associated with the bar code on the Production IG Report 660 or glass label 670 is then automatically imported from the scanner to a computer on the network 216 , and used by the software 510 to update the calculated operation data 538 .
  • the scanned Production IG Report and associated cart 54 is then tracked and rescanned as it enters the kanban 55 staging area 56 in the assigned glazing line 62 , thereagain updating the calculated operation data 538 .
  • the software 510 and calculated operation data 538 accounts for all of the IG units listed in the cart 54 report and the operator provides further reassurance during the report or label scanning operation.
  • a glazing line 62 operator will then scan the Production IG Report 660 or glass label 670 as it leaves the kanban 55 staging area 56 , automatically initiating an update to the calculated operations data 538 .
  • the MCT will be visually displayed on any terminal associated with the computer network 216 and displays the estimated machine completion time for each machine schedule 528 in the IG department 25 and glazing department 60 .
  • the operator at a particular machine may select, for example a fourth schedule in the cutting glass station 28 in the list of schedules 528 for the cutting machine.
  • the terminal would display the MCT in the fourth schedule in the example, showing 1 hour 20 minutes, indicating that the glass cutting for the forth schedule is calculated to be completed in 1 hour and 20 minutes.
  • the calculated MCT can be altered to include or exclude scheduled production breaks, such as lunch, time between shifts, or breaks.
  • the calculated MCT time excludes unscheduled machine downtime.
  • the amount of time scheduled for production breaks could be altered in the software 510 .
  • the MST for the spacer frame production station 30 represents the earliest possible time it could be started based on components being supplied from the glass cutting station 28 and muntin bar station 32 . For example, if the MST for the spacer frame production station 30 indicates a time of 2 hours and 10 minutes at a network terminal 216 , this corresponds to glass and muntin components that are required will be completed in 2 hours and 10 minutes for that particular schedule.
  • the MPR monitors actual machine output, excluding delays that exceed an Anomaly Threshold (AT).
  • AT Anomaly Threshold
  • an AT is set at 10 minutes, and the cutting glass station 28 has been producing schedules 528 at an average rate of 400 lites per hour for the previous three hours. If a 30 minute lunch break were to subsequently occur, which exceeds the AT, the software 510 would average the lites produced per hour until lunch started and store the average as the MPR value. Monitoring would not commence again until after the lunch break and cutting resumed. A new MPR would not be stored until units ran for a prescribed period of time, for example, one hour without a breach of the AT.
  • the AT is a prescribed period that can be varied for each machine, staging area 56 such as the kanban area 55 , or line based particular needs. Any time below the AT is considered normal production delays and is averaged in the MPR. Any time above the AT is considered an irregularity and will be excluded from the MPR. The AT prevents lunches, breaks, and time between shifts from influencing the MPR time.
  • the MPR can further be calculated over a number of machines and assembly lines.
  • the MPR can be measured from the time a schedule 528 starts at the cutting glass station 28 until the cart 54 is scanned into the kanban 55 staging area 56 .
  • the MPR captures glass cutting, spacer fabrication, glass washing, IG assembly, IG carting, IG patch, and IG fill.

Abstract

A method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation. The method includes compiling a plurality of orders and converting the plurality of orders into production schedules for operating processes that fabricate the insulating glass units over a prescribed period of time. The method further includes releasing the production schedules to the plurality of processes used to fabricate insulating glass units. The method also includes monitoring production operations data produced as a result of the releasing the production schedules to the plurality of processes used to fabricate the insulating glass units and providing reports used by the monitoring production operations having image readable indicia that are imaged for providing real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units.

Description

    CROSS REFERENCE TO RELATED APPLICATION
  • The present application is a Continuation-in-Part application of currently pending U.S. application Ser. No.: 10/751,382 having a filing date of Jan. 5, 2004 entitled “Glass Production Sequencing” claiming priority as a Continuation-in-Part of U.S. application Ser. No. 10/646,191, entitled “Glass Optimization” filed Aug. 22, 2003. The present application claims priority to, and incorporates in their entireties both of the above-identified applications for all purposes.
  • FIELD OF THE INVENTION
  • The present invention concerns a method and apparatus for controlling production run sequences of insulating glass units.
  • BACKGROUND ART
  • Window manufacturers typically receive orders that include a variety of different sizes and types of windows and/or patio doors. The different sizes and types of windows and/or patio doors require different sizes and types of insulating glass units (IGs) that are assembled into a frame or sash to form a completed window or patio door at one or more glazing lines. The window manufacturers separate and group the orders for the IGs into regular or planned production runs. The regular or planned production runs are scheduled to be manufactured in a certain sequence on a certain future date, usually within one to three business days ahead.
  • Variables in the manufacturing process rarely allow the regular production runs to be manufactured in the exact planned sequence. For example, rush orders for important customers and remake orders that occur when IGs break are often prioritized, changing the sequence of the production runs. The operational status of machines used to make the components of the IGs may also cause the sequence of the regular or planned production runs to be altered. Further, demand fluctuations, such as a shortage at one of the glazing lines may cause the sequence of the regular or planned production runs to be altered. As a result, a supervisor of an IG production line must constantly monitor each of the manufacturing variables and modify the sequence of the production runs accordingly.
  • Current methods employed by IG supervisors for monitoring IG manufacturing variables and modifying production run sequences are slow, inaccurate and confusing. The existing methods typically rely on informal communications, such as word of mouth, handwritten documents and manual data entry. Use of these non-automated forms of communication often confuse operators, tie up machines and delay standard manufacturing procedures. Use of these informal communication methods cause production efficiencies to drop even further while new employees are being trained or new machines are being commissioned.
  • The glass lites that are needed to construct the IGs are separated and grouped into scheduled production batches or runs. For each production batch, the glass lites are further grouped and arranged to be cut from large stock glass sheets to achieve the highest yield. The process of grouping and arranging glass lites to be cut from stock glass sheets to achieve the highest yield is called glass optimization.
  • Glass optimization is usually performed by a computer executing a computer program. The output from the glass optimization process is a control program that is sent to a computer-controlled cutting table. The glass optimization software outputs a computer program that optimizes one or more production batches containing patterns of lites arranged on stock glass sheets. The cutting table automatically scores the glass according to each pattern. Each production batch normally contains one or more glass layout patterns that provide a lower yield than desirable.
  • These Low Yield Patterns or Low Yield Sheets significantly reduce the yield of entire production batches resulting in higher manufacturing costs due to wasted glass. Waste is particularly expensive when manufacturing windows from increasingly popular specialty glasses such as Low-E or self-cleaning materials.
  • Today, there are several existing methodologies used to increase glass yields. Unfortunately, each method presents one or more problems to manufacturing operations. The methods and their resulting problems are described below.
      • a) Standard dimensioned lites called filler lites can be introduced to scheduled production batches to fill-in unused space on the stock glass sheets. The glass optimization software determines where filler lites can be inserted when creating the initial programmed patterns. Because fillers are inserted prior to the actual manufacturing process, the number and type of filler lites rarely meet actual production demand. Too few filler lites starve production lines while too many fillers create storage and quality problems.
      • b) Adding different sizes of large sheets can be stocked to increase yield.
  • This allows the glass optimization software to pick the size of stock sheets that produce the best yield. Although this method enhances yield, it also increases inventory space and costs while decreasing throughput (more glass sizes to shuttle in and out).
      • c) Certain cutting tables allow the sizes and types of lites from Low Yield Sheets to be manually entered at the cutting table controller with the sizes and types of other of selected lites, then re-optimized to increase yields.
  • Although these features provide flexibility and increase yield, they also cause the cutting table to remain idle during the manual entry process.
  • This greatly reduces production throughput and efficiency.
  • SUMMARY OF THE INVENTION
  • In accordance with one exemplary embodiment of the claimed invention is a method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation. The method comprises compiling a plurality of orders and converting the plurality of orders into production schedules for operating a plurality of processes that fabricate the insulating glass units over a prescribed period of time. The method further includes releasing the production schedules to the plurality of processes used to fabricate insulating glass units. The production schedules are accessible to users through a computer network. The method also includes monitoring production operations data produced as a result of the releasing the production schedules to the plurality of processes used to fabricate the insulating glass units and providing reports used by the monitoring production operations having image readable indicia that are imaged for providing real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units.
  • In accordance with another exemplary embodiment of the claimed invention includes computer-readable media having computer-executable instructions for performing a method optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation, the instructions comprising the step of producing a plurality of production schedules for equipment and assembly operations used to fabricate windows and window components over a prescribed period of time. The instructions further comprise releasing the production schedules to the equipment and assembly operations used to fabricate window and window components. The production schedules are accessible to users through a computer network. The instructions also comprise calculating production operations data associated with the productions schedules. The calculating of the production operations includes using information from continuous real-time data collected from tracking material and components through the equipment and assembly operations used to fabricate window and window components.
  • In accordance with yet another exemplary embodiment of the claimed invention is a method for controlling production schedules of insulating glass units, components, and materials in equipment and assembly operations comprising the steps of compiling a plurality of new, remake, and rush orders used to fabricate insulating glass units and converting the plurality of orders into production schedules for operating a plurality of equipment and assembly operations that fabricate the insulating glass units over a prescribed period of time. The method further includes releasing the production schedules to the plurality of equipment and assembly operations that fabricate insulating glass units, the production schedules being accessible to operators and management through a computer network and monitoring production operations data produced as a result of the releasing the production schedules to the plurality of equipment and assembly operations and real-time feedback information. The monitoring production operations data includes: monitoring individual machine production rates used to fabricate the insulating glass units; monitoring individual machine completion rates used to fabricate the insulating glass units; monitoring individual kanban arrival times having a known amount of material used to fabricate the insulating glass units; monitoring individual kanban consumption rates of the known amount of material used to fabricate the insulating glass units; and monitoring individual machine start times used to fabricate the insulating glass units. The method further includes the steps of alerting operators and/or management should the materials supplied to one or more of the plurality of equipment or assembly operations fall below a prescribed material queue threshold, creating a material notice condition based on the monitoring production operations data and altering one or more of the production schedules based on the material notice condition.
  • These and other objects and advantages of the system constructed in accordance with an exemplary embodiment of the invention is more completely described in conjunction with the accompanying drawings.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 is a schematic representation of a window and/or door manufacturing facility;
  • FIG. 2 is a schematic representation of a window and/or door manufacturing facility equipped with a system for controlling production run sequences of insulating glass units;
  • FIG. 3 is a schematic representation of a user interface by means of which an operator controls production run sequences;
  • FIG. 4 is a schematic representation of a user interface by means of which an operator controls production run sequences;
  • FIG. 5 is a schematic representation of a user interface by means of which an operator controls production run sequences;
  • FIG. 6 is a flow chart that illustrates one method of controlling production run sequences;
  • FIG. 7 is a schematic representation of a cutting station located within a window or door manufacturing facility;
  • FIG. 8 is a schematic of a user interface by means of which an operator sets up cutting operations at the FIG. 1 cutting station;
  • FIGS. 9-15 are schematic depictions of glass sheets illustrating layouts of lites to be cut from the sheets at the cutting station;
  • FIGS. 16A and 16B are flowcharts for optimizing lite layouts on glass sheets of a production run;
  • FIGS. 17A and 17B are flowcharts illustrating a process for managing and optimizing material flow and equipment utilization through the production process of FIG. 2 in accordance with the present invention; and
  • FIG. 18 illustrates a printing operation for a plurality of reports for providing information to the production process of FIG. 2 in accordance with the present invention.
  • DETAILED DESCRIPTION
  • The disclosed invention provides an integrated software and apparatus solution used in the manufacture of windows and/or doors for dynamically monitoring manufacturing variables and controlling production sequences using central production control workstation 10 (FIG. 2).
  • FIG. 1 schematically illustrates a window and/or door manufacturing facility 12. The facility 12 includes a front end system or terminal 14 where orders for windows and/or doors are entered and window assembly is scheduled. The front end system 14 provides orders 16 to an insulating glass unit (IG) production control terminal 18. The orders 16 may include regular production orders 20, rush orders 22, and remake orders 24. The rush orders 22 are orders that are prioritized, usually due to a customer demand. The remake orders 24 are entered when an IG 25, a component of an IG, or a finished window or door 58 is damaged. In the exemplary embodiment, remake orders are provided directly to the central control workstation 18 by an electronic communication 19 from a glazing line or a window component processing station (FIG. 2). The regular production orders 20 are orders that have not been tagged as a rush order or a re-make order.
  • The production control terminal 18 receives the orders 16 as input and creates a sequence of runs of insulating glass units to be produced at an insulating glass unit (IG) department 26. In the illustrated embodiment, the IG department includes several insulating glass component processing machines or stations that construct IG components and assemble the IG components to create IGs. In the illustrated embodiment, the IG component processing stations include a glass cutting station 28, a spacer frame production station 30, a muntin bar production station 32, a muntin bar assembly station 34, a glass washing station 36, an IG assembly station 38, an oven 40, a gas fill station 42, and a patching station 44. Glass lites 46, spacer frames 48, and muntin bars 50 are constructed at the glass cutting station 28, the spacer frame production station 30, and the muntin bar production station respectively. The glass lites, spacer frames, and muntin bar grids 50 are assembled to form IGs at the IG assembly station 38. The IGs are fed through the oven/press 40, which presses the IG to a predetermined thickness and heats the adhesive/sealant that secures the lites to the spacer frame. The IGs are then filled with an inert gas at the gas fill station 42 and patched at the patching station 44. An IG department supervisor 45 is responsible for managing each of the IG component processing stations to ensure that demands for IGs by a glazing department 60 are met.
  • To simplify the disclosure of this inventive method and apparatus, the term glazing is to be interpreted as installing a glass lite or IG in any window or door component and the term sash is to be interpreted as any window or door component that surrounds a glass lite.
  • Once patched, the finished IGs are placed on carts 54 in a staging area 56. The carts 54 in the staging area 56 form a visual kanban system 55, providing production personnel with a visual signaling system by monitoring the number of carts in the staging area assigned to an assembly line in a glazing department 60. More specifically, the IGs are taken from the carts 54 and are assembled with window sash and frames or doors in the glazing department 60 to construct completed windows and/or doors 58. Assembly of an IG to a window or door sash and/or a frame is broadly referred to herein as glazing. The glazing department 60 includes several discrete glazing lines 62.
  • FIG. 2 illustrates a window and/or door manufacturing facility 12 equipped with a system 64 for controlling production run sequences of insulating glass units. In the embodiment illustrated by FIG. 2, the production control terminal 18 receives orders electronically as indicated by arrow 66 from the front end system 14. The control terminal 18 electronically sends and receives information to and from the glass component processing machines as indicated by arrow 68. The front end system 14 and the control terminal 18 receive demand information electronically from the glazing lines as indicated by arrows 70, 72 respectively. This information includes a number of runs 74 in a queue 76 for each glazing line. The control terminal 18 also receives remake requirement information from the glazing lines as indicated by arrow 78. Additional remake information may be provided from one or more of the stations in the IG department.
  • In the exemplary embodiment, the production control terminal 18 is a controller or ancillary computer including a programmable device in communication with a programmable device 80 located at each window component processing station and a programmable device 82 located at the plurality of glazing lines. In the exemplary embodiment, programmable devices 80 are electrically coupled to controllers of window component processing stations that include compatible machine controllers. This allows the sequence of these window processing stations to be altered automatically. Compatible machines automatically run the next production run in the sequence, if configured for Auto Sequencing. Such window component processing stations include the glass cutting station 28, the spacer frame production station 30, the muntin bar production station 32, and the oven 40, in the exemplary embodiment. Non-compatible machines utilize the satellite programmable devices 80 to alert the operator of the new production run sequence. Such stations may include a muntin bar assembly station 34, the glass washing station 36, an IG assembly station 38, a gas fill station 42, and a patching station 44.
  • Referring to FIGS. 3-5, the status of the runs of IGs, the status of the insulating glass component processing machines, and the queue of insulating glass units to be assembled at each glazing line can be viewed at the production control terminal 18 or workstation. The screen illustrated by FIG. 3 provides the IG supervisor with the status of complete IG production runs, the status of runs of IG components, and the status of completed IG runs in queue at the glazing lines. Column 400 provides the IG supervisor with the overall status of IG production runs. Column 402 provides the IG supervisor with the status of runs of muntin bars that correspond to each overall IG production run. Column 404 provides the IG supervisor with the status of runs of glass lites that correspond to each overall IG production run. Column 406 provides the IG supervisor with the status of runs of spacer frames that correspond to each overall IG production run. Column 408 provides the IG supervisor with the status of the IG runs of at the gas fill and patching station. Column 410 provides the IG supervisor with the glazing line number or description and the status of each completed IG production run at the identified glazing line.
  • The screen of FIG. 4 provides the IG supervisor with the status of the completed IG runs in the glazing queue of each glazing line. On the screen illustrated by FIG. 4, columns 412, 414, 416, 418 provide the status of each run 420 of assembled IGs in the queues 422 of glazing lines 1, 2, 3, and 4 respectively. The stiphing and cross-hatching of FIG. 4 corresponds to the legend shown in FIG. 3.
  • The screen illustrated by FIG. 5 provides the IG supervisor with the status of each production run 424 in the production run queue for each window component processing station. Column 428 provides the status of the muntin runs. Column 430 provides the status of the glass cutting runs. Column 432 provides the status of the spacer frame runs. Column 434 provides the status of the IGs at the gas fill and patch station.
  • The IG supervisor alters the sequence of runs based on one of the status of the runs, the status of one or more of the glass processing machines, and the queue of insulating glass units at the glazing line at the production control terminal. In the exemplary embodiment, the following manufacturing variables can all be monitored at the production control terminal 18:
      • a) The status of sequenced regular, rush or remake production runs.
      • b) The status of sequenced muntin production runs and machine status at the muntin bar production Station 32.
      • c) The status of sequenced glass production runs and machine status.
      • d) The status of sequenced spacer production runs and machine status.
      • e) The status of sequenced IG patch production runs.
      • f) The status of production runs in each glazing line queue.
      • g) Electronic requests to prioritize specific regular, rush or remake production runs.
  • Referring to the flow chart of FIG. 6, in the exemplary embodiment production run sequences are downloaded 86 from the terminal 14 to the control terminal 18. Software running on the control terminal 18 determines 88 whether the runs received from the customer terminal 14 are larger than a user defined Run Size Parameter. If the number of IG units per production run surpass the number of IG units specified in the Production Run Size Parameter, the method automatically divides or segments 90 the runs into segments based on the size parameter setting. In the exemplary embodiment, the Production Run Size Parameter is entered by a user via a setup menu. Some customers create one or more very large daily production runs. For those customers, the system automatically segments large runs from the terminal 14 into a number of smaller runs, identifying each as some subset of the whole. Small production runs, typically matching the IG cart size, provide the flexibility required to properly level-load the glazing lines.
  • The IG supervisor may view 92 the IG Department Queue at the Central Workstation 18 (see FIG. 3). This view provides the supervisor with an accurate snapshot of the status of all scheduled IG production runs via color codes (These codes are designated by cross-hatching and stiphing different patterns in the Figures). The supervisor can view the production run status 94 of each of the machines, the overall production run status and requests to prioritize a particular run 96 from satellite devices 80, 82, and low queue conditions 98 from the glazing lines. A low queue condition at a glazing line may be automatically detected or entered through a satellite device by a glazing line worker. In the exemplary embodiment, the supervisor uses the information on the display to determine 100 whether the current production sequence maintains an efficient, uninterrupted production flow through the IG Department. If the current production sequence would not result in an efficient, uninterrupted production flow through the IG Department, the IG supervisor changes 102 the production control sequence at the control workstation 18. In an alternate embodiment, the determination 100 of whether action needs to be taken and the run sequence changed 102 is performed by the software in the control terminal 18. Each status or sequence changed at the central control terminal 18 is updated 104 automatically and provided 106 to all of IG component processing stations and the glazing lines by compatible machine software and/or the satellite programmable devices 80, 82.
  • In the exemplary embodiment, a change of the production run sequence at the central workstation, immediately changes the corresponding sequences in a database maintained at the workstation 18 and display of compatible machine controllers and satellite programmable devices. Compatible machines automatically run 110 the next production run in the sequence, if configured for auto sequencing. Non-compatible machines utilize satellite programmable devices to alert the operator of the new production run sequence.
  • In the exemplary embodiment, required labels and reports are automatically printed 112 for each production run using a compatible printer. A parameter in the setup menu determines how far in advance to print labels and reports for each production run. The IG supervisor may manually print selected reports via a user-friendly menu. The labels and reports will accompany the IG through the manufacturing process. In the exemplary embodiment, an operator may use the graphical display to print and/or display 114 labels, reports, and/or low queue condition statistics.
  • A number of factors dictate whether the IG supervisor (or the computer program loaded on the control terminal 18) needs to change the production run sequence. Examples include ease of production, delivery priority, component availability and glazing line requirements. Based on these factors, the IG supervisor uses a graphical “drag and drop” function on the screen of the control terminal 18 to change the production run sequence. In the exemplary embodiment, the system will not allow the IG supervisor to change the sequence of any completed or partially completed production runs. A partially completed production run has either been started at the machine or is reserved using a Production Run Look-Ahead Parameter. This parameter reserves a specific number of the next available production runs for glass optimization purposes or to give the IG supervisor sufficient time to print and deliver labels and reports to the production floor. The Production Run Look-Ahead Parameter is entered via a setup menu.
  • In the exemplary embodiment, the system may allow the IG supervisor to display the glazing line queue (see FIG. 4). The supervisor uses this display to monitor the level-loading of each glazing line and changes the run sequence as needed to prevent low queue conditions at a given glazing line. In one embodiment, the system includes a glazing line monitoring system. In this embodiment, the system automatically monitors each glazing line queue 422 for a “low queue condition.” This condition is met when the production runs 104 waiting to be glazed fall below a parameter set for each glazing line 62 in the setup menu. In the exemplary embodiment, the low queue condition is automatically detected by identifying runs of assembled insulating glass units that are delivered to each glazing line and identifying runs of assembled insulating glass units that are assembled to windows, or otherwise processed at each glazing line. In the exemplary embodiment, this identifying of runs of IGs that enter and exit the glazing lines is performed by scanning an identification label.
  • If the “low queue condition” is met, the system automatically highlights the next available production run for that glazing line in red at the central workstation 18. This highlighting alerts the IG supervisor that he should change the sequence to prevent shutting down the glazing line.
  • In one embodiment, glazing line personnel may also use satellite programmable devices 82 located at each glazing line to force a “low queue condition”. This feature allows the glazing line personnel to request the next available production run for that glazing line from the IG Department at the terminal 18. Glazing line personnel may also use satellite programmable devices to prioritize specific regular, rush or remake production runs. The request alerts the IG supervisor by highlighting the corresponding production run on the display of the central workstation 18.
  • In the exemplary embodiment, the invention allows the IG supervisor to react to manufacturing variables by modifying the sequence of the production runs using a graphical drag and drop function. The software uses the input from the drag and drop function to create a new or altered production run sequence. Once the software has completed creating the new production run sequence, the system automatically performs the following tasks:
  • a) Changes the sequence of the production runs in the central workstation 18 database and updates the display (see FIGS. 3 and 4).
  • b) Changes the sequence of the production runs in each manufacturing machine with a compatible database and updates the display (see FIG. 5).
  • c) Changes the sequence of the production runs in the database of each satellite programmable device adjacent to non-compatible machines or manual production areas and updates the display (see FIG. 5).
  • d) Changes the sequence of the production runs in the database of each satellite programmable device at the glazing lines (see FIG. 4).
  • e) Prints the appropriate production paperwork and labels to accompany the corresponding IG.
  • The system includes three software tools that help manage each glazing line queue. The first tool provides a parameter in the setup menu to dictate the minimum number of production runs staged for each glazing line. The system uses this parameter to automatically alert the IG supervisor of a “low queue condition” by highlighting the next available production run for that glazing line in red when the number of production runs in queue falls below the set minimum number. The IG supervisor will then make the decision to change the priority of that production run.
  • The second tool provides statistics describing the number of “low queue conditions” for each glazing line over time. This provides the IG supervisor with information to increase or reduce the size of the queue limit for each glazing line These tools help the IG supervisor optimize the size of the glazing line queues to achieve the highest throughput.
  • The third tool allows glazing line personnel to use a satellite programmable device 82 to force a “low queue condition” or to prioritize a specific regular, rush or remake production run for a particular glazing line. The request alerts the IG supervisor by highlighting the corresponding production run on the display of the central workstation.
  • The disclosed system provides the IG supervisor with real-time, accurate and simple tools to monitor manufacturing variables and control production run sequences. The supervisor will easily accomplish existing tasks in a fraction of the time, using accurate real-time data. Production run sequences will be set in plenty of time to continue standard manufacturing procedures without any loss of production efficiency.
  • One component of the disclosed system is a glass optimization module for increasing the yield of glass cutting runs during window or door manufacture, or other manufacture requiring glass lites. An exemplary glass optimization module or program automatically recognizes and optimizes Low Yield Sheets by adding glass lites from other production batches as well as lites entered or selected at the cutting station 28. The exemplary glass optimization module also automatically creates, tracks, selects and re-cuts remnant sheets of glass if the process is unable to add sufficient lites to eliminate Low Yield Sheets from a production batch.
  • The FIG. 7 cutting station 28 includes a controller 212 that provides the cutting station operator an option of easily selecting filler lite sizes that can be automatically inserted into each production batch. The controller is coupled to a display or breakout monitor 214 that graphically alerts the cutting table operator(s) which cart and slot to place each lite as it is cut. The controller 212 and breakout monitor 214 also graphically alert the cutting table operator(s) where to place or remove remnant sheets for subsequent processing. The controller and breakout monitor also graphically alert the cutting table operator(s) which temporary cart slot to place or remove lites for subsequent processing.
  • In addition, the system tracks and reports yield, throughput and filler lite information in real-time to the cutting table display or monitor 214 as well as other computers by means of a network 216 which allows the controller 212 to communicate with other computers in the manufacturing facility, including the central control terminal 18. These other computers include computer-controlled manufacturing devices at other workstations and computer software for controlling the entire manufacturing process.
  • FIG. 7 depicts representative apparatus for optimizing the fabrication of products that include lites cut from the glass sheets. The cutting station 28 including a moveable cutting head 220 supported for movement with respect to a glass sheet 222 (FIG. 9) positioned on a cutting table 224 with respect to the cutting head 220 from which glass lites are cut. The same controller 212 that updates the display or monitor 214 is also responsible for controlling the movement with respect to the cutting table of the cutting head 220.
  • FIG. 9 shows a representative sheet 222 having a number of lites 230-233 scheduled to be cut from specified locations on the sheet 222. Typical dimensions (prior to cutting) for a sheet such as the sheet 222 shown in FIG. 9 are 72 inches by 84 inches. Other standard sizes are 96″ by 130″ and 48″ by 60″.
  • The sheet 222 is removed by an operator from one of two racks 240, 241 (FIG. 7) positioned in relation to the cutting table 224. The sheet is placed on its edge at the side or at the end of a free fall table 242. The table 242 has a relatively smooth and soft top surface onto which the glass sheet falls. From its position on the table the sheet is automatically transferred to the cutting table 224. While on the cutting table 224 the sheet 222 is cut by the cutting head and then moved to a break out table 244. At the break out table 244 an operator breaks out the lites from the glass sheet 222.
  • As seen in FIG. 7, a number of carts 250-253 are positioned with respect to the cutting station 28 for storing lites as they are cut from a glass sheet 222 by the cutting head 220. The controller 212 or another ancillary computer includes software running on a processor, which performs a number of tasks used by the system for making the glass cutting process more efficient. The controller lists a number of batches wherein each batch requires a specified number and type of glass lites for use in fabricating products in an associated job. The controller 212 (or ancillary computer) and breakout monitor 214 displays a pattern of lites to be cut from a first set of glass sheets to fulfill the lite requirements for one batch and during cutting prompts the operator to place the lites for that job into a single one of the four carts 250-253.
  • The controller 212 or ancillary computer is capable of recognizing and adjusting to under utilized glass sheets. In accordance with one exemplary embodiment of the invention, under utilized glass sheet is any sheet where less than 70% of the sheet has lites allocated for a given job. The sheet 222 depicted in FIG. 9 is an underutilized glass sheet having free space 260 with no lites designated to be cut for the batch that the sheet 222 is associated with. The four lites 230 that have been designated for a particular batch have been labeled with the designation “P” to indicate that they are associated with a particular production batch. These four lites 230-233 take up much less than the 70% cutoff.
  • As explained more fully below, the controller 212 or ancillary computer responds to recognition of such an underutilized sheet by laying out a pattern of lites to be cut to fulfill other lite requirements, possibly the other requirements one or more additional batches in a queue of such batches. The controller utilizes at least some of the free space 260 on the underutilized glass sheets of a first batch by designating usage of the free space 260 for other batches. The controller 212 or ancillary computer then completes the designated lites for those other or subsequent batches by laying out other glass sheets from which to cut other lites in that subsequent batch(es). This process, of course, takes into account the lites that have already been designated from the underutilized sheet or sheets of the previous batch or batches.
  • Operation of the Cutting Station 28
  • The software running on the controller or ancillary computer of the cutting station begins heuristically optimizing a next production batch in a queue of such batches by identifying a Low Yield Sheet if it exists. The controller or ancillary computer automatically calculates how to fill the sheet according to a list of priorities exemplified by the flowchart 310 in FIGS. 16A and 16B. To help illustrate the process of FIGS. 16A and 16B, in FIGS. 9-15 the glass lites are labeled with designators depending on where in the list of priorities these lites are identified for inclusion onto a Low Yield Sheet.
  • The highest priority is a regular production batch lite P. A next highest priority is a local remake or MDI lite L. Three such lites 31 are depicted in FIG. 4. An MDI lite is typically made in response to a request due to breakage or a prior knowledge of a need by the cutting station operator. MDI lite information is entered by the operator at controller 212 using a keypad. A local remake is typically required because a lite is broken at the cutting table. Local remake information is entered by the operator using pushbuttons to highlight the lite that needs to be replaced on the breakout monitor or on the controller display.
  • A next highest priority lite inserted into the Low Yield Sheet is a production run look ahead lite LA. Two such lites 232 are depicted in FIG. 11. A typical manufacturing sequence of batches will have need for lites from the same type of glass in multiple batches. The system recognizes this need by inserting lites for subsequent batches on a Low Yield Sheet. These are called look ahead lites LA because the system “looks ahead” to subsequent jobs for lites to add to a Low Yield Sheet. As the operator breaks out the lites from a sheet the viewing monitor 214 tells the operator where he or she should put that look ahead lite. This is typically in the form of a cart slot number at the cutting station.
  • The next priority lite added to a Low Yield Sheet is a filler lite F. Filler lites are certain sizes and glass types that are commonly used in production. The system adds filler lites to Low Yield Sheets to increase yield. They are stored in close proximity to the cutting table. The number of filler lites needed is noted on the display. (See FIG. 16) As the number of filler lites that have been cut increases, the corresponding number of filler lites that are needed decreases and the video display will be updated until the desired number of filler lites has been cut. When a production batch calls for a lite with the size and glass type of a filler lite, an appropriate filler lite can be quickly retrieved from the storage area. Although the depictions of FIGS. 9-15 suggest that the controller places lites of a similar nature together on the glass sheet, the controller may rearrange the lites on a pattern to increase yield and may for example intersperse lites of different types next each other on the glass sheet.
  • The next priority added to a Low Yield Sheet is a temporary lite T. A temporary lite is designated as a lite to be stored in a temporary cart until a cart for it's production batch has been placed at the cutting table in the positions illustrated in FIG. 7 by carts 250, 251, 252, or 253.
  • The next priority added to a Low Yield Sheet is a remnant R. A remnant is designated as the remaining area of the large stock glass sheet that can be stored and used later in the optimization process. The invention will instruct the cutting table if and how to cut the remnant for easier storage and store the position and size information of the remnant for subsequent optimization.
  • During the glass optimization process 310 (which takes place prior to cutting) depicted in the flow chart of FIGS. 16A and 16B, the controller optimizes glass usage to reduce waste during glass cutting utilizing the sequence of priorities. The invention may also heuristically change the sequence of priorities based on input gathered via a computer network from other machines or programmable devices.
  • The cutting table operator presses 312 a function key on the controller. The controller responds by displaying 314 a graphical display 270 similar to FIG. 8. Listed on the display 270 is a Production Run Look-Ahead Parameter 272. This parameter corresponds to how many production batches the controller will look-ahead for lites to increase the yield on Low Yield Sheets. The yield (as a percentage) that the controller uses to determine a Low Yield Sheet is entered during the initial setup of the invention. Each production run typically corresponds to one cart. Therefore, if the Production Run Look-Ahead parameter displays the number ‘3’, the operator knows to place 316 three carts 250, 251, 252 around the cutting table.
  • The display 270 (FIG. 8) also includes a Temporary Cart Look-Ahead Parameter 274. If a number other than 0 is displayed, the operator places 318 a temporary cart or carts (cart 253 for example) at the cutting table. The displayed parameter indicates the number of additional production runs (in addition to the production run look ahead) to be checked with the look-ahead function. Assuming the temporary cart look ahead is other than zero, the Breakout Monitor will display which slot in the temporary cart the operator should place the lites identified from those production batches. In a typical application there is only one temporary cart for storing lites from multiple additional batches. When those additional batches are cut, the operator is prompted to move an already cut lite from its slot in the temporary cart and moved to its appropriate (and now in place) production run cart location or slot.
  • The operator views the Filler Lites Needed table 276 and enters the desired number of filler lites. Whenever possible, the invention adds the sizes of filler requested to Low Yield Sheet until the requested amount of filler lites is satisfied.
  • The operator views the Auto Sequencing Parameter. If “off”, the operator cannot change the order of the production batches in the queue. The order of the production batches will be determined by external software. If “on”, the operator may rearrange 322 the order of any production batches not started. Color coding of the display of FIG. 2 indicates which production batches in a list 280 are not started.
  • The operator then presses 324 the cycle start button. The cutting table will begin the next production run in the queue. The invention automatically identifies Low Yield Sheets and will calculate how to get the best yield. The sequence of steps 330 depicted in FIG. 16B inform the operator which type of sheet to drop on the cutting table. The invention will follow a user-defined sequence of priorities to determine how to increase the yield by adding lites to the Low Yield Sheet from different sources. The invention adds lites from MDI (manual data input), local remake entry, future production runs and standard sizes (filler lites). The invention may also heuristically change the sequence of priorities based on input gathered via a computer network from other machines or programmable devices. If any Low Yield Sheets remain and the Remnant Management Parameter is “on”, the invention will determine if the lites on the low yield sheet can more efficiently fit on a stored remnant sheet in a manner that eliminates the low yield condition. If so, the controller and breakout monitor alert the operator to load the corresponding stored remnant sheet from a remnant storage and retrieval system 45 having a cart for storing remnant sheets. The size and configuration of the Remnant Sheet Queue will be entered during the initial setup of the invention.
  • After the cutting table scores the sheet and it remains a Low Yield Sheets and the Remnant Management Parameter is “on” and there is room to store another remnant sheet on the remnant sheet cart, the system scores the largest rectangle possible in the unused area of the Low Yield Pattern. Via the breakout monitor, the system alerts the operator to transfer the remnant sheet to a manual, semi-automatic or automatic remnant storage and retrieval system 245. The breakout monitor also indicates which cart and slot (standard or temporary cart) to place each lite via text and color coding.
  • The operator presses another function key at the cutting table controller to return to the previous screen.
  • The invention also tracks and reports yield, throughput and filler lite information in real-time to the cutting table display as well as other computers, computer-controlled devices and computer software.
  • Glass Demand System
  • FIGS. 17A and 17B are flowcharts illustrating a process for managing and optimizing material flow and equipment utilization through a production process in accordance with the present invention. In particular, FIGS. 17A and 17B illustrate a glass demand system 500 that includes software 510 or other forms of computer readable media used to efficiently manage the material flow through the production process as illustrated in FIG. 2. In one example embodiment, the software 510 is loaded onto the computer network 216, which would include all computer terminals related to the production operation, such as the central workstation 18, satellite devices 80, and programmable devices 82.
  • In the first operation of the demand system 500 the software 510 is executed in the network 216 at 512. The software 510 supports user created merge files 514 comprising regular production orders 20, rush orders 22 and remake orders 24. The merge files 514 are structured to conveniently allow for frequent changes and/or creation of new merge files for each day or shift of production as depicted at 516. For each shift of production or during a production run, the software 510 converts the merge files into machine readable programs or machine schedules 524 at 520. The machine schedules 524 are then placed into a demand pre-release folder 518 at 522.
  • The demand pre-release folder 518 containing the machine schedules 524 are now readily accessible by a supervisor and/or operator via the software 510 at 526 linked to the computer network 216. At this point 528, the supervisor and/or operator can evaluate whether the machine schedules 524 are satisfactory or require modification. In one embodiment, the machine schedules 524 would be modified before the start of a shift, however, it would not depart from the spirit and scope of the claimed invention to enable the supervisor and/or operator to modify the machine schedules after a shift has started or during production run.
  • If the machine schedules 524 are not satisfactory the supervisor and/or operator will resequence or reassign (to alternate machines or kanbans) the machine schedules 524 to modified schedules 530 at 532. Several factors in the production operation could render the machine schedules 524 unsatisfactory requiring resequencing or reassignment 532. For example, changes in production orders 16, including regular production orders 20 and/or rush orders 22 and/or remake orders 24 could influence such required changes, low queue 76 signals or indications in the IG runs 74 for particular glazing lines 62 could provoke a change, or machine breakdown in the IG department 26 or glazing department 60. The resequencing or reassignment 532 by the supervisor or operator can be achieved at any network 216 terminal by a similar “drag and drop” application in the software 510, as previously discussed. The resequencing or reassignment 532 may change the order or amount of materials being processed at any individual line or machine within the IG department 26. This could include for example, changes to the assembly operation 38, cutting station 28, or oven 40 in the IG department 26. Similarly, changes may occur at the glazing lines 62 as a result of the resequencing or reassignment process 532.
  • The modified schedules 530 or satisfactory machine schedules 524 mature into final schedules 534 and are released to the machines, equipment, IG lines located within the IG department 26 or computer workstations on computer network 216 at 536. The software 510 then calculates operations data 538 based on the final schedules 534 and the sequences are released to the equipment and assembly lines. The software 510 further uses the calculated operations data 538 to perform several different computations relating to the production operations shown in FIG. 2, including:
      • a) the machine production rate (MPR) for various equipment, for example: the glass cutting station(s) 28 (lites per unit of time); spacer frame production station 30; muntin machine(s) 32 (grids per unit time); and assembly 38 (IG units per unit of time);
      • b) the machine completion time (MCT) for each schedule (hours and minutes from the current time) for cutting stations 28, spacer frame production station 30, muntin machines 32, and assembly operations 28;
      • c) the machine start time (MST) for each schedule (hours and minutes from the current time) for cutting stations 28, spacer frame production station 30, muntin machines 32, and assembly operations 28 (the machine start time (MST) for each spacer frame production station 30 schedule (hours and minutes from the current time) is based on estimates of when the glass and muntin will be available for the spacer frame production station 30);
      • d) the kanban arrival time (KAT) for each schedule in a kanban 55 (hours and minutes from the current time); and
      • e) the kanban consumption rate (KCR) the number of IG units removed from the carts 54 in the kanban 55 staging area 56 (IG units used per unit of time).
  • The calculated operations data 538 relating to the various operations described above, are monitored at 542 to help prevent future Out-of-Glass conditions 544 that could arise. For example, if the kanban 55 staging area 56 has only one hour of glass left in a particular glazing line 62 based on the KCR and the next cart 54 with IG units is scheduled to arrived at the kanban 55 in two hours an Out-of-Glass condition 544 is detected and the software 510 will issue an Out-of-Glass Alert 550, indicating and notifying production personnel when the kanban staging area 56 will run out of glass. In one embodiment, the software 510 will calculate which schedule or schedules 524 will be advanced 552 in the production sequence upon issuing the alert 550. In another embodiment, as shown at 554, the software 510 in anticipation of the alert 550 will calculate which schedule or schedules 524 will be advanced in the production sequence and may be automatically advanced at 556 by the software 510. In yet another embodiment, the operator or supervisor manually elects at 558 which schedule or schedules 524 will be advanced in the production sequence as a result of the calculation 552 provided by the software 510 or based on the supervisor/operator's own independent decision or instruction by another person or source.
  • The software 510 additionally supports a printing operation 600 that provides a number of reports that are used by both production personnel and management. The reports assist in providing real-time information 539 to the production operations data 538 via manual and automatic scanning of material throughput (discussed further below) during the manufacturing process.
  • The print operation 600 produces an IG Cart Report 610 for schedules 524 having at least one cut glass lite. The IG Cart Report is printed typically near the cutting glass station 28 when the schedule starts to assist production personnel in tracking the schedules 528 through the production operation. The print operation 600 also produces an IG Cart Office Report 620 for schedules 528 with all purchased glass. The IG Cart Office Report 620 is typically printed in a manager's office 625 when the schedule is released to the cutting glass station 28 for assisting management personnel in tracking the schedules 528 through the production operation. The print operation 600 also produces a Purchased Glass Report 630 for schedules 528 with at least one purchased glass lite. The Purchased Glass Report 630 is typically printed near the cutting glass station 28 when the schedule 528 starts. The Purchased Glass Report 630 assists production personnel in tracking the glass used by the various schedules 528. The print operation 600 also provides a Purchased Glass Office Report 640 for schedules 528 with all purchased glass. The Purchased Glass Office Report 640 is typically printed in the manager's office 625 when the schedule is released to the cutting glass station 28 for assisting management personnel in tracking the schedules 528 through the production operation. The print operation 600 also provides a Production Muntin Report 650. The Production Muntin Report 650 typically prints near the muntin bar station 32. The Production Muntin Report 650 assists production and management personnel in tracking the raw materials used in forming the muntin bars. The print operation 600 also provides a Production IG Report 660. The Production IG Report 660 typically prints near the spacer frame production station 30. The Production IG Report 660 assists production and management personnel in tracking the raw materials being used to make the IG assemblies in the spacer frame production stations 30. The print operation 600 also provides a Glass Label Report 670 consisting of one or more individual glass labels. The Glass Label Report 670 typically prints near the spacer frame production station 30. The Glass Label Report 670 assists production and management personnel in tracking the IG assemblies as they are routed through the production operation.
  • The above reports can also be used to assist in the accuracy of the calculated operations data 538 by providing real-time data. For example, a patch operator assigned to the patch station 44 will scan data (using either a stationary or portable scanner device) such as a bar code relating to the IG assemblies on the Production IG Report 660 or glass label 670 as it leaves the patching station 44. The content associated with the bar code on the Production IG Report 660 or glass label 670 is then automatically imported from the scanner to a computer on the network 216, and used by the software 510 to update the calculated operation data 538. The scanned Production IG Report and associated cart 54 is then tracked and rescanned as it enters the kanban 55 staging area 56 in the assigned glazing line 62, thereagain updating the calculated operation data 538. The software 510 and calculated operation data 538 accounts for all of the IG units listed in the cart 54 report and the operator provides further reassurance during the report or label scanning operation. A glazing line 62 operator will then scan the Production IG Report 660 or glass label 670 as it leaves the kanban 55 staging area 56, automatically initiating an update to the calculated operations data 538.
  • The MCT will be visually displayed on any terminal associated with the computer network 216 and displays the estimated machine completion time for each machine schedule 528 in the IG department 25 and glazing department 60. For example, the operator at a particular machine may select, for example a fourth schedule in the cutting glass station 28 in the list of schedules 528 for the cutting machine. The terminal would display the MCT in the fourth schedule in the example, showing 1 hour 20 minutes, indicating that the glass cutting for the forth schedule is calculated to be completed in 1 hour and 20 minutes. The calculated MCT can be altered to include or exclude scheduled production breaks, such as lunch, time between shifts, or breaks. The calculated MCT time excludes unscheduled machine downtime. The amount of time scheduled for production breaks could be altered in the software 510.
  • The MST for the spacer frame production station 30 represents the earliest possible time it could be started based on components being supplied from the glass cutting station 28 and muntin bar station 32. For example, if the MST for the spacer frame production station 30 indicates a time of 2 hours and 10 minutes at a network terminal 216, this corresponds to glass and muntin components that are required will be completed in 2 hours and 10 minutes for that particular schedule.
  • The MPR monitors actual machine output, excluding delays that exceed an Anomaly Threshold (AT). For example, an AT is set at 10 minutes, and the cutting glass station 28 has been producing schedules 528 at an average rate of 400 lites per hour for the previous three hours. If a 30 minute lunch break were to subsequently occur, which exceeds the AT, the software 510 would average the lites produced per hour until lunch started and store the average as the MPR value. Monitoring would not commence again until after the lunch break and cutting resumed. A new MPR would not be stored until units ran for a prescribed period of time, for example, one hour without a breach of the AT.
  • The AT is a prescribed period that can be varied for each machine, staging area 56 such as the kanban area 55, or line based particular needs. Any time below the AT is considered normal production delays and is averaged in the MPR. Any time above the AT is considered an irregularity and will be excluded from the MPR. The AT prevents lunches, breaks, and time between shifts from influencing the MPR time.
  • The MPR can further be calculated over a number of machines and assembly lines. For example, the MPR can be measured from the time a schedule 528 starts at the cutting glass station 28 until the cart 54 is scanned into the kanban 55 staging area 56. In this example, the MPR captures glass cutting, spacer fabrication, glass washing, IG assembly, IG carting, IG patch, and IG fill.
  • Although an exemplary embodiment of the invention has been described with a degree of particularity, it is the intent that the invention includes all modifications and alterations from the disclosed design falling within the spirit or scope of the appended claims.

Claims (21)

1. A method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation, comprising the step of:
a) compiling a plurality of orders used to fabricate insulating glass units;
b) converting said plurality of orders into production schedules for processes used to fabricate the insulating glass units over a prescribed period of time;
c) releasing said production schedules to the processes used to fabricate insulating glass units, said production schedules being accessible to users through a computer network;
d) monitoring production operations data produced as a result of said releasing the production schedules to the processes used to fabricate insulating glass units, and
e) providing reports used by said monitoring production operations having image readable indicia that are imaged for providing real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units.
2. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of monitoring production operations data includes monitoring individual machine production rates.
3. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of monitoring production operations data includes monitoring individual machine completion rates.
4. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of monitoring production operations data includes monitoring individual machine start times.
5. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of monitoring production operations data includes monitoring individual kanban arrival times.
6. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of monitoring production operations data includes monitoring individual kanban consumption rates.
7. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 further comprises the step of alerting users should the materials supplied to one or more of the processes fall below a prescribed material queue threshold based on said monitoring production operations data.
8. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 7 wherein the step of alerting users should the materials supplied to one or more of the processes fall below a prescribed material queue threshold further includes calculating which of said production schedules should be advanced in the production operation as a result of said alerting.
9. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 8 wherein the step of calculating which of said production schedules should be advanced in the production operation is automatically initiated without user input.
10. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of providing reports having image readable indicia that are imaged for real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units includes providing each individual kanban with said image readable indicia.
11. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 10 wherein the step of providing reports having image readable indicia that is imaged for real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units includes providing material within each of the individual kanbans with said image readable indicia.
12. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 further comprises updating said production operations data as a result of information provided from reading the image readable indicia.
13. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 wherein the step of providing reports having image readable indicia that are imaged for providing real-time data for tracking material flow to, from, and through the processes used in the fabrication of insulating glass units further comprises scanning the image readable indicia as it enters and exits each process in the fabrication of insulating glass units.
14. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 3 wherein the step of monitoring individual machine completion rates further includes providing users with access for viewing any current, future, or past machine completion rate for any process used in the fabrication of insulating glass units for any production schedule.
15. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 3 wherein the step of monitoring individual machine completion rates further includes allowing for the addition or exclusion of scheduled machine downtime.
16. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 1 further comprises allowing manual alterations in said production schedules.
17. The method for optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation of claim 2 wherein the step of monitoring production operations data includes monitoring individual machine production rates further comprises providing an anomaly threshold variable that when exceeded influences said individual machine production rates values.
18. Computer-readable media having computer-executable instructions for performing a method optimizing material flow and equipment utilization in the fabrication of insulating glass units in a production operation, the instructions comprising the step of:
a) producing a plurality of production schedules for equipment and assembly operations used to fabricate windows and window components over a prescribed period of time;
b) releasing said production schedules to the equipment and assembly operations used to fabricate window and window components, said production schedules being accessible to users through a computer network;
c) calculating production operations data associated with said productions schedules, the calculating of the production operations includes using information from continuous real-time data collected from tracking material and components through the equipment and assembly operations used to fabricate window and window components.
19. The computer-readable media of claim 18 wherein the instructions for performing the step of calculating production operations data further comprises alerting users should materials or components supplied to one or more of the equipment and/or assembly operations fall below a prescribed material queue threshold prescribed in the computer-readable media.
20. The computer-readable media of claim 18 wherein the instructions for performing the step of calculating production operations data further comprises altering sequences in said productions schedules should materials or components supplied to one or more of the equipment and/or assembly operations fall below a prescribed material queue threshold prescribed in the computer-readable media.
21. A method for controlling production schedules of insulating glass units, components, and materials in equipment and assembly operations comprising the steps of:
a) compiling a plurality of new, remake, and rush orders used to fabricate insulating glass units;
b) converting said plurality of orders into production schedules for operating a plurality of equipment and assembly operations that fabricate the insulating glass units over a prescribed period of time;
c) releasing said production schedules to the plurality of equipment and assembly operations that fabricate insulating glass units, said production schedules being accessible to operators and management through a computer network;
d) monitoring production operations data produced as a result of said releasing the production schedules to the plurality of equipment and assembly operations and real-time feedback information, the monitoring production operations data comprising:
i) monitoring individual machine production rates used to fabricate the insulating glass units;
ii) monitoring individual machine completion rates used to fabricate the insulating glass units;
iii) monitoring individual kanban arrival times having a known amount of material used to fabricate the insulating glass units;
iv) monitoring individual kanban consumption rates of the known amount of material used to fabricate the insulating glass units; and
v) monitoring individual machine start times used to fabricate the insulating glass units;
e) alerting operators and/or management should the materials supplied to one or more of the plurality of equipment or assembly operations fall below a prescribed material queue threshold creating a material notice condition based on said monitoring production operations data; and
f) altering one or more of said production schedules based on said material notice condition.
US11/652,747 2003-08-22 2007-01-12 Glass demand scheduling system Abandoned US20070112451A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US11/652,747 US20070112451A1 (en) 2003-08-22 2007-01-12 Glass demand scheduling system

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US64619103A 2003-08-22 2003-08-22
US10/751,382 US7167767B2 (en) 2003-08-22 2004-01-05 Glass production sequencing
US11/652,747 US20070112451A1 (en) 2003-08-22 2007-01-12 Glass demand scheduling system

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US10/751,382 Continuation-In-Part US7167767B2 (en) 2003-08-22 2004-01-05 Glass production sequencing

Publications (1)

Publication Number Publication Date
US20070112451A1 true US20070112451A1 (en) 2007-05-17

Family

ID=34279053

Family Applications (2)

Application Number Title Priority Date Filing Date
US10/751,382 Active 2024-09-02 US7167767B2 (en) 2003-08-22 2004-01-05 Glass production sequencing
US11/652,747 Abandoned US20070112451A1 (en) 2003-08-22 2007-01-12 Glass demand scheduling system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US10/751,382 Active 2024-09-02 US7167767B2 (en) 2003-08-22 2004-01-05 Glass production sequencing

Country Status (2)

Country Link
US (2) US7167767B2 (en)
CA (1) CA2476713C (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070270996A1 (en) * 2006-05-18 2007-11-22 Roise Geoffrey J System and method for cutting-stock optimization across schedules and batches
US20090139163A1 (en) * 2007-12-04 2009-06-04 Intigral, Inc. Insulating glass unit
US20090139164A1 (en) * 2007-12-04 2009-06-04 Intigral, Inc. Insulating glass unit
US20090139165A1 (en) * 2007-12-04 2009-06-04 Intigral, Inc. Insulating glass unit
US20100269544A1 (en) * 2007-08-22 2010-10-28 Hp3 Software, Inc Glass production line having dynamic production control and a tempering furnace with a dedicated delivery device and a method of controlling a glass production line tempering furnace
US20110238195A1 (en) * 2009-09-29 2011-09-29 Hp3 Software, Inc. Dynamic, Lean Insulated Glass Unit Assembly Line Scheduler
US20120078406A1 (en) * 2009-03-10 2012-03-29 Lg Chem, Ltd. Process for preparation of quadrangle unit
US20130060371A1 (en) * 2011-09-01 2013-03-07 Sap Ag Next generation sequencing management
US8401689B1 (en) * 2008-07-15 2013-03-19 Hp3 Software, Inc. Dynamic global scheduler system for a glass production line
US20140025189A1 (en) * 2012-07-20 2014-01-23 Honeywell Asca Inc. Method for Target Driven Charting in Flat Sheet Industries
EP2738636A2 (en) 2012-11-29 2014-06-04 Waldemar Knittel Glasbearbeitungs GmbH Method for producing flat glass sheets and flat glass sheet manufacturing system

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7246423B1 (en) * 2002-12-19 2007-07-24 Simonton Building Products, Inc. System and method for in-line production of insulated glass units for custom windows
US7873918B2 (en) * 2005-07-07 2011-01-18 Konica Minolta Business Technologies, Inc. Method and apparatus for displaying workflow
US20070288125A1 (en) * 2006-06-09 2007-12-13 Mks Instruments, Inc. Power Over Ethernet (Poe) - Based Measurement System
PL1900695T3 (en) * 2006-08-17 2012-05-31 Albat Wirsam Software Ag Process and apparatus for cutting glass sheets
US20080226850A1 (en) * 2007-03-15 2008-09-18 Ged Integrated Solutions, Inc. Alternating Spacer Frame Line Control
US8359116B2 (en) * 2009-09-11 2013-01-22 Sap Ag Production management system
CA2738325A1 (en) * 2010-05-03 2011-11-03 Pmc Software Inc. Method and system for cutting glass
US8627856B2 (en) 2010-06-28 2014-01-14 Integrated Automation Systems, Llc Continuous gas filling process and apparatus for fabrication of insulating glass units
US8460489B2 (en) * 2010-08-13 2013-06-11 Ged Integrated Solutions, Inc. Flexible film application for decorative coatings
FR3002529B1 (en) * 2013-02-22 2015-02-20 Saint Gobain METHOD FOR CUTTING ONE OR MORE WINDOWS
CN104021499B (en) * 2013-03-01 2018-03-09 中芯国际集成电路制造(上海)有限公司 Semiconductor manufacturing control method
US10328594B2 (en) 2015-12-07 2019-06-25 Cardinal Ig Company Muntin bar fabrication system
TWI718705B (en) * 2019-10-15 2021-02-11 薩摩亞商紘織國際有限公司 A system that combines dynamic production and plant material transportation management
CN112433512A (en) * 2020-11-03 2021-03-02 佛山市德力泰科技有限公司 Control system and control method of energy-saving glazing line
CN113618536A (en) * 2021-07-27 2021-11-09 佛山市汉腾自动化有限公司 Glass deep processing production line connection method

Citations (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5099431A (en) * 1989-10-23 1992-03-24 International Business Machines Corporation Automated re-work shop order scheduling system
US5315509A (en) * 1989-10-23 1994-05-24 International Business Machines Corporation Artificial intelligence system for item analysis for rework shop orders
US5373451A (en) * 1992-03-17 1994-12-13 Fujitsu Limited Rack transport control apparatus for a manufacturing line
US5446671A (en) * 1993-10-22 1995-08-29 Micron Semiconductor, Inc. Look-ahead method for maintaining optimum queued quantities of in-process parts at a manufacturing bottleneck
US5567258A (en) * 1989-09-29 1996-10-22 Morton International Limited Manufacture of insulated glass units
US5570292A (en) * 1994-02-14 1996-10-29 Andersen Corporation Integrated method and apparatus for selecting, ordering and manufacturing art glass panels
US5573618A (en) * 1994-12-23 1996-11-12 Cardinal Ig Company Method for assembling custom glass assemblies
US5612886A (en) * 1995-05-12 1997-03-18 Taiwan Semiconductor Manufacturing Company Ltd. Method and system for dynamic dispatching in semiconductor manufacturing plants
US5880960A (en) * 1997-01-27 1999-03-09 Taiwan Semiconductor Manufacturing Company, Ltd. Method to improve WIP balance in a manufacturing line
US6068720A (en) * 1998-07-01 2000-05-30 Edge Seal Technologies, Inc. Method of manufacturing insulating glass units
US6198980B1 (en) * 1998-11-06 2001-03-06 John Costanza Institute Of Technology System and method for designing a mixed-model manufacturing process
US6278901B1 (en) * 1998-12-18 2001-08-21 Impresse Corporation Methods for creating aggregate plans useful in manufacturing environments
US6294044B1 (en) * 1997-12-22 2001-09-25 Technoplast Kunststofftechnik Gmbh Apparatus for the production of window frames
US6321133B1 (en) * 1998-12-04 2001-11-20 Impresse Corporation Method and apparatus for order promising
US6353769B1 (en) * 1999-03-22 2002-03-05 Taiwan Semiconductor Manufacturing Company Method for allocating lot priority by ranking lots as a function of budget queue time in a manufacturing control system
US6381509B1 (en) * 1998-11-02 2002-04-30 Mattec, Inc. Automatic manufacturing monitoring and tracking
US6490494B1 (en) * 2000-02-18 2002-12-03 Mitsubishi Denki Kabushiki Kaisha Method and apparatus for processing order control
US6546364B1 (en) * 1998-12-18 2003-04-08 Impresse Corporation Method and apparatus for creating adaptive workflows
US6580963B2 (en) * 2000-12-13 2003-06-17 Thermwood Corporation System and method for automatically tracking and utilizing excess material on a CNC machining system
US6583509B2 (en) * 1999-06-01 2003-06-24 Applied Materials, Inc. Semiconductor processing techniques
US6594535B1 (en) * 1999-01-11 2003-07-15 Demand Flow Institute, Llc Material and inventory control system for a demand flow process
US6615097B2 (en) * 2000-07-12 2003-09-02 Mitsubishi Denki Kabushiki Kaisha Production management system
US20030200130A1 (en) * 2002-02-06 2003-10-23 Kall Jonathan J. Suite of configurable supply chain infrastructure modules for deploying collaborative e-manufacturing solutions
US6647307B1 (en) * 2002-11-07 2003-11-11 Taiwan Semiconductor Mfg. Co. Ltd. Method for controlling queue time constraints in a fabrication facility
US20030233163A1 (en) * 2002-06-18 2003-12-18 Glass Equipment Development, Inc. Window or door manufacturing method and apparatus
US6757577B1 (en) * 2000-08-08 2004-06-29 Taiwan Semiconductor Manufacturing Co., Ltd. System and method for managing work-in-process (WIP) workload within a fabrication facility
US6782295B2 (en) * 2000-05-04 2004-08-24 The Regents Of The University Of California Optimizing the availability of a buffered industrial process
US6816746B2 (en) * 2001-03-05 2004-11-09 Dell Products L.P. Method and system for monitoring resources within a manufacturing environment
US20040225507A1 (en) * 1999-11-03 2004-11-11 Timothy Jay Smith Delivery management system
US6880960B2 (en) * 2003-03-26 2005-04-19 E'sam Co., Ltd. Side mirror cover and side mirror body
US20050182506A1 (en) * 2002-04-10 2005-08-18 Billco Manufacturing Incorporated Glass processing equipment with dynamic continuous production control system
US6973359B2 (en) * 2002-09-19 2005-12-06 Synchrono, Inc. Demand-driven scheduling system and method
US20060009990A1 (en) * 2004-07-08 2006-01-12 Mccormick John K Method, apparatus, data structure and system for evaluating the impact of proposed actions on an entity's strategic objectives
US7089071B2 (en) * 1994-05-27 2006-08-08 Infor International Limited Method and apparatus for scheduling work orders in a manufacturing process
US20060253312A1 (en) * 1998-10-21 2006-11-09 Lilly Michael P System and method for throughput measurement
US7246423B1 (en) * 2002-12-19 2007-07-24 Simonton Building Products, Inc. System and method for in-line production of insulated glass units for custom windows

Patent Citations (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5567258A (en) * 1989-09-29 1996-10-22 Morton International Limited Manufacture of insulated glass units
US5099431A (en) * 1989-10-23 1992-03-24 International Business Machines Corporation Automated re-work shop order scheduling system
US5315509A (en) * 1989-10-23 1994-05-24 International Business Machines Corporation Artificial intelligence system for item analysis for rework shop orders
US5373451A (en) * 1992-03-17 1994-12-13 Fujitsu Limited Rack transport control apparatus for a manufacturing line
US5446671A (en) * 1993-10-22 1995-08-29 Micron Semiconductor, Inc. Look-ahead method for maintaining optimum queued quantities of in-process parts at a manufacturing bottleneck
US5570292A (en) * 1994-02-14 1996-10-29 Andersen Corporation Integrated method and apparatus for selecting, ordering and manufacturing art glass panels
US7089071B2 (en) * 1994-05-27 2006-08-08 Infor International Limited Method and apparatus for scheduling work orders in a manufacturing process
US5573618A (en) * 1994-12-23 1996-11-12 Cardinal Ig Company Method for assembling custom glass assemblies
US5612886A (en) * 1995-05-12 1997-03-18 Taiwan Semiconductor Manufacturing Company Ltd. Method and system for dynamic dispatching in semiconductor manufacturing plants
US5880960A (en) * 1997-01-27 1999-03-09 Taiwan Semiconductor Manufacturing Company, Ltd. Method to improve WIP balance in a manufacturing line
US6294044B1 (en) * 1997-12-22 2001-09-25 Technoplast Kunststofftechnik Gmbh Apparatus for the production of window frames
US6068720A (en) * 1998-07-01 2000-05-30 Edge Seal Technologies, Inc. Method of manufacturing insulating glass units
US20060253312A1 (en) * 1998-10-21 2006-11-09 Lilly Michael P System and method for throughput measurement
US6381509B1 (en) * 1998-11-02 2002-04-30 Mattec, Inc. Automatic manufacturing monitoring and tracking
US6198980B1 (en) * 1998-11-06 2001-03-06 John Costanza Institute Of Technology System and method for designing a mixed-model manufacturing process
US6321133B1 (en) * 1998-12-04 2001-11-20 Impresse Corporation Method and apparatus for order promising
US6278901B1 (en) * 1998-12-18 2001-08-21 Impresse Corporation Methods for creating aggregate plans useful in manufacturing environments
US6546364B1 (en) * 1998-12-18 2003-04-08 Impresse Corporation Method and apparatus for creating adaptive workflows
US6594535B1 (en) * 1999-01-11 2003-07-15 Demand Flow Institute, Llc Material and inventory control system for a demand flow process
US6353769B1 (en) * 1999-03-22 2002-03-05 Taiwan Semiconductor Manufacturing Company Method for allocating lot priority by ranking lots as a function of budget queue time in a manufacturing control system
US6583509B2 (en) * 1999-06-01 2003-06-24 Applied Materials, Inc. Semiconductor processing techniques
US20040225507A1 (en) * 1999-11-03 2004-11-11 Timothy Jay Smith Delivery management system
US6490494B1 (en) * 2000-02-18 2002-12-03 Mitsubishi Denki Kabushiki Kaisha Method and apparatus for processing order control
US6782295B2 (en) * 2000-05-04 2004-08-24 The Regents Of The University Of California Optimizing the availability of a buffered industrial process
US6615097B2 (en) * 2000-07-12 2003-09-02 Mitsubishi Denki Kabushiki Kaisha Production management system
US6757577B1 (en) * 2000-08-08 2004-06-29 Taiwan Semiconductor Manufacturing Co., Ltd. System and method for managing work-in-process (WIP) workload within a fabrication facility
US6580963B2 (en) * 2000-12-13 2003-06-17 Thermwood Corporation System and method for automatically tracking and utilizing excess material on a CNC machining system
US6816746B2 (en) * 2001-03-05 2004-11-09 Dell Products L.P. Method and system for monitoring resources within a manufacturing environment
US20030200130A1 (en) * 2002-02-06 2003-10-23 Kall Jonathan J. Suite of configurable supply chain infrastructure modules for deploying collaborative e-manufacturing solutions
US20050182506A1 (en) * 2002-04-10 2005-08-18 Billco Manufacturing Incorporated Glass processing equipment with dynamic continuous production control system
US20030233163A1 (en) * 2002-06-18 2003-12-18 Glass Equipment Development, Inc. Window or door manufacturing method and apparatus
US6973359B2 (en) * 2002-09-19 2005-12-06 Synchrono, Inc. Demand-driven scheduling system and method
US6647307B1 (en) * 2002-11-07 2003-11-11 Taiwan Semiconductor Mfg. Co. Ltd. Method for controlling queue time constraints in a fabrication facility
US7246423B1 (en) * 2002-12-19 2007-07-24 Simonton Building Products, Inc. System and method for in-line production of insulated glass units for custom windows
US6880960B2 (en) * 2003-03-26 2005-04-19 E'sam Co., Ltd. Side mirror cover and side mirror body
US20060009990A1 (en) * 2004-07-08 2006-01-12 Mccormick John K Method, apparatus, data structure and system for evaluating the impact of proposed actions on an entity's strategic objectives

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8010216B2 (en) * 2006-05-18 2011-08-30 Roise Geoffrey J System and method for cutting-stock optimization across schedules and batches
US8862261B1 (en) * 2006-05-18 2014-10-14 Geoffrey J. Roise Method and system for cutting-stock optimization across schedules and batches
US20070270996A1 (en) * 2006-05-18 2007-11-22 Roise Geoffrey J System and method for cutting-stock optimization across schedules and batches
US8244394B2 (en) * 2007-08-22 2012-08-14 Hp3 Software Incorporated Glass production line having dynamic production control and a tempering furnace with a dedicated delivery device and a method of controlling a glass production line tempering furnace
US20100269544A1 (en) * 2007-08-22 2010-10-28 Hp3 Software, Inc Glass production line having dynamic production control and a tempering furnace with a dedicated delivery device and a method of controlling a glass production line tempering furnace
US20090139163A1 (en) * 2007-12-04 2009-06-04 Intigral, Inc. Insulating glass unit
US20090139164A1 (en) * 2007-12-04 2009-06-04 Intigral, Inc. Insulating glass unit
US20090139165A1 (en) * 2007-12-04 2009-06-04 Intigral, Inc. Insulating glass unit
US8401689B1 (en) * 2008-07-15 2013-03-19 Hp3 Software, Inc. Dynamic global scheduler system for a glass production line
US20120078406A1 (en) * 2009-03-10 2012-03-29 Lg Chem, Ltd. Process for preparation of quadrangle unit
US20130317638A1 (en) * 2009-03-10 2013-11-28 Lg Chem, Ltd. Process for preparation of quadrangle unit
US9104191B2 (en) * 2009-03-10 2015-08-11 Lg Chem, Ltd. Process for preparation of quadrangle unit
US9417618B2 (en) * 2009-03-10 2016-08-16 Lg Chem, Ltd. Process for preparation of quadrangle unit
US8731699B2 (en) * 2009-09-29 2014-05-20 Hp3 Software, Inc. Dynamic, lean insulated glass unit assembly line scheduler
US20110238195A1 (en) * 2009-09-29 2011-09-29 Hp3 Software, Inc. Dynamic, Lean Insulated Glass Unit Assembly Line Scheduler
US9443215B2 (en) * 2011-09-01 2016-09-13 Sap Se Next generation sequencing management
US20130060371A1 (en) * 2011-09-01 2013-03-07 Sap Ag Next generation sequencing management
US9202181B2 (en) * 2012-07-20 2015-12-01 Honeywell Asca Inc. Method for target driven charting in flat sheet industries
US20140025189A1 (en) * 2012-07-20 2014-01-23 Honeywell Asca Inc. Method for Target Driven Charting in Flat Sheet Industries
DE102012023266A1 (en) * 2012-11-29 2014-06-05 Glaswerke Arnold Gmbh & Co. Kg Method for producing flat glass panes and flat glass pane production line
EP2738636A3 (en) * 2012-11-29 2015-09-16 Waldemar Knittel Glasbearbeitungs GmbH Method for producing flat glass sheets and flat glass sheet manufacturing system
EP2738636A2 (en) 2012-11-29 2014-06-04 Waldemar Knittel Glasbearbeitungs GmbH Method for producing flat glass sheets and flat glass sheet manufacturing system
DE102012023266B4 (en) 2012-11-29 2017-03-30 Glaswerke Arnold Gmbh & Co. Kg Method for producing flat glass panes and flat glass pane production line

Also Published As

Publication number Publication date
US7167767B2 (en) 2007-01-23
CA2476713C (en) 2015-12-01
CA2476713A1 (en) 2005-02-22
US20050043838A1 (en) 2005-02-24

Similar Documents

Publication Publication Date Title
US20070112451A1 (en) Glass demand scheduling system
US6954676B2 (en) Window or door manufacturing method and apparatus
CN111027876A (en) Process production plan scheduling system under distributed production mode
US9621621B2 (en) System, apparatus and method for activity guidance and monitoring
CN104240041A (en) Method and system for scheduling a manufacturing process
CN101706886A (en) Order-driven Single-piece small-batch combined flow production method for processing workshop
CN111415069B (en) Discrete manufacturing process intelligent real-time scheduling method
US7206656B2 (en) Glass optimization
CN114066308B (en) Production work order adjusting method and device and electronic equipment
CN108445853B (en) Productivity sharing workshop based on cloud data
US8401689B1 (en) Dynamic global scheduler system for a glass production line
JPH05143613A (en) Production planning system
CN110989511A (en) Tool life visual early warning method
JP3218530B2 (en) Numerical control processing method and numerical control processing system
CA2467436C (en) Glass optimization
EP2919080B1 (en) Job plan display system
CN112070378A (en) Production scheduling management method based on logic priority principle by utilizing computer
KR20210054936A (en) Signboard production process management system and operating method thereof
JPH04347769A (en) Process management device
CN115660618B (en) Maintenance flow optimization method based on corrugated paper equipment and related equipment
JPH09212556A (en) Operating instruction method in process schedule
JP3056516B2 (en) production management system
CN114418525A (en) Method and system for controlling online process of drawer
CN115081774A (en) System and method for compiling production plan and monitoring production execution condition
CN116796939A (en) Production scheduling management system

Legal Events

Date Code Title Description
AS Assignment

Owner name: GED INTEGRATED SOLUTIONS, INC.,OHIO

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:CLAYTON, BYRON;DORSCH, PAUL;REEL/FRAME:018804/0507

Effective date: 20070111

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION