CN105203984B CN201410262275.2A CN201410262275A CN105203984B CN 105203984 B CN105203984 B CN 105203984B CN 201410262275 A CN201410262275 A CN 201410262275A CN 105203984 B CN105203984 B CN 105203984B
Authority
CN
China
Prior art keywords
voltage
transformer
module
secondary side
measurement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410262275.2A
Other languages
Chinese (zh)
Other versions
CN105203984A (en
Inventor
李�瑞
宋述勇
马振国
郝伟
孙瑞浩
张悦
刘杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority to CN201410262275.2A priority Critical patent/CN105203984B/en
Publication of CN105203984A publication Critical patent/CN105203984A/en
Application granted granted Critical
Publication of CN105203984B publication Critical patent/CN105203984B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to a kind of wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer, its interval measurement apparatus (4) connects the secondary circuit of conventional current transformer (3), conventional voltage transformer (1) by combining unit (2), so as to obtain the electric current that conventional current transformer (3) secondary side of the string branch road flows into combining unit (2), and the voltage of conventional voltage transformer (1) secondary side access combining unit (2), and data are passed into measurement head station (5) by WLAN interface.Finally by head station display panel (9), the data that the data that WLAN interface is sent and the MMS nets from transformer station are obtained are contrasted.This instrument only needs 1 to 2 people to operate, it is most important that the wattless power measurement situation of bus measure and control device that can conveniently to being set in protective chamber is checked, verified, and ensures the net synchronization capability of the measurement of each bar branch road of bus.It can be applied to the verification field of the intelligent station based on traditional transformer.

Description

The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer
Technical field
The present invention relates to a kind of bus reactive power rate tester, more particularly to a kind of intelligent power transformation based on traditional transformer The tester for 3/2 wiring bus reactive power rate of standing.
Background technology
Preceding power network development is to after this current stage, and the state estimation work of power network is one very meaningful and very Important work.In current electric grid in super extra-high voltage intelligent substation 330kV, 500kV part or 1000kV parts, extensively should It is 3/2 main wiring mode.Because traditional transformer has many advantages, such as, thus widely use, or even in intelligent substation Without using new IED (intelligent power equipment) electronic mutual inductor, but use traditional transformer.
The secondary side connection of transformer is located at the combining unit in the Intelligent control cabinet in switch yard by this mode of connection, And then current signal is become into digital optical signal by combining unit, the measure and control device and others being sent in protective chamber are secondary Device.Because the area of super extra-high voltage intelligent substation is very big, the intelligence in the floor space of the part of only 330kV and the above farther out The distance of energy switch board to protective chamber has typically been above 100 meters.
The secondary device of intelligent substation is made up of three layer of two net, refers to three-layer equipment two-tier network, if two host's mistakes Journey layer network, station level network.Process-level network (is solved networking transmission to simulate by GOOSE nets (transmission switching value) and SV nets Amount) composition.Station level mainly uses intelligent substation 61850MMS manufacture messaging systems, is to be based on IEC-22850 agreements Intelligent substation communication basis.MMS is a kind of application layer protocol.Realizing between the equipment for coming from different manufacturers has Interoperability, makes the system integration become simple, conveniently.At present, it is of wide application.
, it is necessary to which the measurement performance to the measurement and control instrument at scene carries out live inspection during dispatching of power netwoks and operational management Look into.Currently, when the part to 3/2 bus carries out DATA REASONING, there is the method for several measurements.First method is:Use biography The measuring instrument of system needs the measurement of a string of branch roads then a string of branch roads, and measurement complete strips bus, which respectively goes here and there the duration of branch road, about to be needed Want 15 minutes to 16 minutes.After measurement is over, calculated according to the result of measurement.In this process, due on power network Flow situations have occurred and that change, cause the result of measurement very inaccurate or even these data can not be used.Second method, All arrange one to two full-time staff using often string branch road, branch road of often going here and there is equipped with a measuring instrumentss, and by talk back equipment and When contact, with ensure it is each string branch road measurement data while property.Using second method, required manpower is more, with 10 string branch Exemplified by the bus on road, then 10~8 people are needed, while record data.Even so, or it cannot be guaranteed that while metric data Property.
The content of the invention
(1) technical problem to be solved
The technical problem to be solved in the present invention is how to provide a kind of based on traditional wiring of transformer intelligent transformer station 3/2 Bus reactive power rate tester, conveniently the reactive power equilibrium of bus measure and control device set in protective chamber is surveyed The progress of amount situation is checked, verified, and ensures metric data while property.
(2) technical scheme
In order to solve the above-mentioned technical problem, the invention provides a kind of wiring of intelligent station 3/2 based on traditional transformer is female Line reactive power tester, it is characterised in that including more than one interval measurement device;
The interval measurement device connection electric current card stream pincers and pressure-wire, pass through the merging in Intelligent control cabinet in transformer station Unit connection conventional current transformer, the secondary circuit of conventional voltage transformer;
The interval measurement device is made up of a set of modular equipment being arranged in a complete enclosure, bag The first CPU module is included, in the periphery of the first CPU module provided with the first chargeable electrical storage device, the first power knob switch, first Clock module, the first watchdog module, for connecting the voltage measurement A/D module in three-phase voltage measurement loop, for connecting three-phase The current measurement A/D module of current measurement circuit, the first WLAN adaptation modules, gps satellite synchronous interface module, the first storage mould Block, indicating lamp module;
The voltage measurement A/D module has voltage measurement circuit Ua, Ub, Uc, Un;
The current measurement A/D module has jaw type current measurement circuit Ia, Ib, Ic, In;
Interval measurement device is stuck in outside the A phase secondary side wiring of conventional current transformer by the way that the first electric current card stream pincers are outer Side, to measure input jaw type current measurement circuit Ia current value, so as to obtain the electricity that secondary side A phases flow into combining unit Stream;The outer B phase secondary sides wiring outside for being stuck in conventional current transformer is clamped by the second electric current card stream, to measure input jaw type Current measurement circuit Ib current value, so as to obtain the electric current that secondary side B phases flow into combining unit;Clamped by the 3rd electric current card stream It is outer to be stuck on the outside of the C phase secondary sides wiring of conventional current transformer, to measure input jaw type current measurement circuit Ic electric current Value, so as to obtain the electric current that secondary side C phases flow into combining unit;Conventional current mutual inductance is stuck in by the way that neutral current card stream pincers are outer On the outside of the secondary side neutral conductor wiring of device, to measure input jaw type current measurement circuit In current value, so as to obtain secondary The side neutral conductor flows into the electric current of combining unit;
Interval measurement device is connected directly between in the A phase secondary side wiring of conventional voltage transformer by first voltage line, For measuring voltage measurement circuit Ua voltage, so as to obtain the voltage that secondary side A phases access combining unit;Pass through second voltage Line is connected directly between in the B phase secondary side wiring of conventional voltage transformer, the voltage for measuring voltage measurement circuit Ub, so that Obtain the voltage that secondary side B phases access combining unit;The C phases two of conventional voltage transformer are connected directly between by tertiary voltage line On secondary side joint line, for measuring voltage measurement circuit Uc voltage, so as to obtain the voltage that secondary side C phases access combining unit; It is connected directly between by neutral conductor pressure-wire in the neutral conductor secondary side wiring of conventional voltage transformer, for measuring voltage measurement Loop Un voltage, so as to obtain the voltage that the secondary side neutral conductor accesses combining unit;
Interval measurement device obtains lock in time by the gps satellite sync cap on gps satellite synchronous interface module, leads to The WLAN WLAN interface crossed in the first WLAN adaptation modules sends to the measurement head station equipped with head station WLAN interface and is spaced Time and electric parameter that measurement apparatus is measured;
What the measurement head station was made up of a set of modular equipment being arranged in a complete enclosure, including second CPU module, the periphery of second CPU module is provided with the second chargeable electrical storage device, second source button switch, second clock Module, the second watchdog module, the 2nd WLAN adaptation modules, the second memory module, MMS Ethernet adaptation modules;
Head station is measured to receive from interval measurement device through wireless by the WLAN interface of the WLAN adaptation modules of head station the 2nd The data that LAN WLAN interface is sent.
Preferably, the wiring bus tester of traditional transformer intelligent transformer station 3/2 includes four interval measurement devices.
The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer that the present invention is provided is verified When, comprise the following steps:
Step one:Interval measurement device is clamped by the first electric current card stream, the second electric current card stream is clamped, the 3rd electric current card stream Pincers, neutral current card stream pincers, the respectively outer A phase secondary sides wiring outside for being stuck in conventional current transformer, B phase secondary side wiring On the outside of outside, the wiring of C phase secondary sides, on the outside of the wiring of the secondary side neutral conductor;
By current measurement A/D module, the inflow of conventional current transformer secondary side A phase, B phase, C phase and the neutral conductor is measured The electric current of combining unit;
Interval measurement device is passed through into first voltage line, second voltage line, tertiary voltage line, neutral conductor pressure-wire, difference It is connected to the A phase secondary sides wiring of conventional voltage transformer, the wiring of B phase secondary sides, the wiring of C phase secondary sides, neutral conductor secondary side In wiring;
By voltage measurement A/D module, the access of conventional voltage transformer secondary side A phase, B phase, C phase and the neutral conductor is measured The voltage of combining unit;
Step 2:Interval measurement device receives the clock signal of synchronous satellite by gps satellite sync cap thereon, and The electric current at the branch road interval, active, idle and its direction under whole time preservation;Interval measurement device is by this branch road interval Electric current, active, idle and its direction, the time tag for adding this moment is packaged into packet together, by wireless local Net WLAN interface is sent to the measurement head station equipped with head station WLAN interface;
Step 3:Measurement head station is linked into the MMS of 3/2nds parts of intelligent substation nets, and when from the net Carve extract be sent on each measure and control device station level by active, the idle and its direction in observing and controlling branch road interval, and pass through MMS In net pair when signal record monitor clock signal in real time, and be stored in inside measurement head station;
Step 4:Measurement head station receives the electricity at each branch road interval that each interval measurement device is sent by WLAN interface Behind stream, active, idle and its direction, it will be sorted according to branch road compartment name, the time sent from WLAN interface is represented respectively Mark, by the time of measuring of same whole time, electric current, active, idle and its direction and from during the measurement that MMS nets are got Between, electric current, active, idle list respectively, and calculate whole piece bus and active power and and reactive power;
Step 5:Measurement head station shows the key parameter of step 4, and and step on its measurement head station display panel Three data are contrasted.
(3) beneficial effect
A kind of wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer of the present invention, including one Above interval measurement device, the interval measurement device connection electric current card stream pincers and pressure-wire, passes through Based Intelligent Control in transformer station Combining unit connection conventional current transformer in cabinet, the secondary circuit of conventional voltage transformer, so as to obtain the string branch road The electric current of conventional current transformer secondary side A phase, B phase, C phase and the inflow combining unit of the neutral conductor, and conventional voltage transformer Secondary side A phase, B phase, C phase and the neutral conductor access the voltage of combining unit, and the data measured are passed to by WLAN interface Measure head station.Finally by the head station display panel of measurement head station, the data that WLAN interface is sent and the MMS nets from transformer station The data got are contrasted.This instrument only needs 1 to 2 people to operate, it is most important that can be conveniently to protection The wattless power measurement situation of the bus measure and control device of small indoor setting is checked, verified, and ensures each bar branch road of bus The net synchronization capability of measurement.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing The accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1:A kind of configuration under a kind of mode of connection of intelligent substation 3/2 based on traditional transformer that the present invention is provided Scheme schematic diagram;
Fig. 2:Structure connection diagram between interval measurement device and combining unit that the present invention is provided;
Fig. 3:The external structure schematic diagram of the measurement head station of the present invention;
Fig. 4:A kind of internal structure schematic diagram for interval measurement device that the present invention is provided;
Fig. 5:A kind of internal structure schematic diagram for measurement head station that the present invention is provided;
In figure:1st, conventional voltage transformer;2nd, combining unit;3rd, conventional current transformer;4th, interval measurement device;5th, survey Measure head station;6th, gps satellite sync cap;7th, WLAN WLAN interface;8th, head station WLAN interface;9th, head station display panel; 10th, neutral current card stream is clamped;11st, the first electric current card stream is clamped;12nd, the second electric current card stream is clamped;13rd, the 3rd electric current card stream is clamped;14、 First voltage line;15th, second voltage line;16th, tertiary voltage line;17th, neutral conductor pressure-wire;18th, the observing and controlling of protective chamber device is filled Put;19th, MMS interface;20th, the first CPU module;21st, the first chargeable electrical storage device;22nd, the first power knob is switched;23rd, One clock module;24th, the first watchdog module;25th, voltage measurement A/D module;26th, current measurement A/D module;27th, the first WLAN Adaptation module;28th, gps satellite synchronous interface module;29th, the first memory module;30th, indicating lamp module;31st, the second CPU module; 32nd, the second chargeable electrical storage device;33rd, second source button switch;34th, second clock module;35th, the second watchdog module; 36th, the 2nd WLAN adaptation modules;37th, the second memory module;38th, MMS Ethernets adaptation module.
Embodiment
Embodiments of the present invention are described in further detail with reference to the accompanying drawings and examples.Following examples are used for Illustrate the present invention, but can not be used for limiting the scope of the present invention.
As shown in figure 1, one kind under the mode of connection of intelligent substation 3/2 based on traditional transformer that the present embodiment is provided Allocation plan schematic diagram;Structure annexation wherein between interval measurement device and combining unit is as shown in Fig. 2 measurement head station 5 external structure schematic diagram is as shown in Figure 3.
The connection electric current card stream pincers of interval measurement device 4 and pressure-wire, pass through the merging list in Intelligent control cabinet in transformer station Member 2 connects conventional current transformer 3, the secondary circuit of conventional voltage transformer 1;
As shown in figure 4, the interval measurement device 4 is a set of modular equipment by being arranged in a complete enclosure Come what is constituted, including the first CPU module 20, it is provided with the first chargeable electrical storage device 21, first in the periphery of the first CPU module 20 Power knob switchs the 22, first clock module 23, the first watchdog module 24, the voltage for connecting three-phase voltage measurement loop Measure A/D module 25, the current measurement A/D module 26 for connecting three-phase current measuring loop, the first WLAN adaptation modules 27, Gps satellite synchronous interface module 28, the first memory module 29, indicating lamp module 30;
The voltage measurement A/D module 25 has voltage measurement circuit Ua, Ub, Uc, Un;
The current measurement A/D module 26 has jaw type current measurement circuit Ia, Ib, Ic, In;
Interval measurement device 4 clamps the A phase secondary side wiring that conventional current transformer 3 is stuck in outside 11 by the first electric current card stream Outside, to measure input jaw type current measurement circuit Ia current value, so that obtaining secondary side A phases flows into combining unit 2 Electric current;Clamped and be stuck in outside 12 on the outside of the B phase secondary sides wiring of conventional current transformer 3 by the second electric current card stream, it is defeated to measure Enter jaw type current measurement circuit Ib current value, so as to obtain the electric current that secondary side B phases flow into combining unit 2;Pass through the 3rd electricity It is stuck on the outside of the C phase secondary sides wiring of conventional current transformer 3, is returned to measure the current measurement of input jaw type outside stream card stream pincers 13 Road Ic current value, so as to obtain the electric current that secondary side C phases flow into combining unit 2;10 wild cards are clamped by neutral current card stream On the outside of the secondary side neutral conductor wiring of conventional current transformer 3, to measure input jaw type current measurement circuit In electric current Value, so as to obtain the electric current that the secondary side neutral conductor flows into combining unit 2;
Interval measurement device 4 is connected directly between the A phase secondary side wiring of conventional voltage transformer 1 by first voltage line 14 On, for measuring voltage measurement circuit Ua voltage, so as to obtain the voltage that secondary side A phases access combining unit 2;Pass through second Pressure-wire 15 is connected directly between in the B phase secondary side wiring of conventional voltage transformer 1, the electricity for measuring voltage measurement circuit Ub Pressure, so as to obtain the voltage that secondary side B phases access combining unit 2;Conventional voltage is connected directly between by tertiary voltage line 16 mutual In the C phase secondary side wiring of sensor 1, for measuring voltage measurement circuit Uc voltage, so that obtaining secondary side C phases accesses merging The voltage of unit 2;It is connected directly between by neutral conductor pressure-wire 17 in the neutral conductor secondary side wiring of conventional voltage transformer 1, For measuring voltage measurement circuit Un voltage, so as to obtain the voltage that the secondary side neutral conductor accesses combining unit 2;
When interval measurement device 4 obtains synchronous by the gps satellite sync cap 6 on gps satellite synchronous interface module 28 Between, by the WLAN WLAN interface 7 in the first WLAN adaptation modules 27 to the measurement head station equipped with head station WLAN interface 8 Time and electric parameter that 5 transmission interval measurement devices 4 are measured;
As shown in figure 5, the measurement head station 5 is made up of a set of modular equipment being arranged in a complete enclosure , including the second CPU module 31, the periphery of second CPU module 31 is provided with the second chargeable electrical storage device 32, second source Button switch 33, second clock module 34, the second watchdog module 35, the 2nd WLAN adaptation modules 36, the second memory module 37, MMS Ethernets adaptation module 38;
Head station 5 is measured to receive from interval measurement dress by the head station WLAN interface 8 of the WLAN adaptation modules 36 of head station the 2nd Put 4 data sent through WLAN WLAN interface 7.
A kind of wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer that the present embodiment is provided, bag Include 4 interval measurement devices.Specifically enter with the wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer During row verification, the quantity of its interval measurement device included is configured according to the string number of branch road, can be 1 of the above Any quantity.
Only illustrate the structure of interval measurement device on wherein one branch road, interval measurement device and conventional current mutual inductance below The connected mode of device, the secondary circuit of conventional voltage transformer, and interval measurement device carry out school to the data on the string branch road The operation principle and process tested.
The interval measurement device 4 in the present embodiment a set of modular is set by be arranged in a complete enclosure For come what is constituted, interval measurement device 4 sets the first chargeable electricity of electrical storage device 21, first in the periphery of the first CPU module 20 Source button switch 22, the first clock module 23, the first watchdog module 24, the voltage survey for connecting three-phase voltage measurement loop Measure A/D module 25, the current measurement A/D module 26 for connecting three-phase current measuring loop, the first WLAN adaptation modules 27, GPS Satellite synchronization interface module 28, the first memory module 29, indicating lamp module 30 are constituted.
The characteristics of this interval measurement device, is equipped with battery, can after fully charging, and can continue a journey work, conveniently exists Outdoor scene carries out not needing external power supply can be carried out under 3/2 mode of connection.
Next is provided with gps satellite synchronous interface module, can cause the data of each interval measurement measurement device and be Data on section at the same time.
WLAN adaptation modules are finally equipped with, the data wirelessly measured are sent by WLAN interface Go out, simplify the wiring at scene.
In the present embodiment, measurement head station 5 is in the periphery of the second CPU module 31 provided with the second chargeable electrical storage device 32, the Two power knobs switch 33, second clock module 34, the second watchdog module 35, the storage of the 2nd WLAN adaptation modules 36, second Module 37, MMS Ethernets adaptation module 38.
The characteristics of this measurement head station, is equipped with chargeable electrical storage device, can after fully charging, and can continue a journey work, side Just scene outdoor under 3/2 mode of connection carries out not needing external power supply can be carried out.
Next is provided with memory module, can store the handled data finished.
WLAN adaptation modules are finally equipped with, the data wirelessly measured are sent by WLAN interface Go out, simplify the wiring at scene.
In intelligent station normal work, the secondary side voltage and conventional current of the collection conventional voltage transformer 1 of combining unit 2 The secondary side current of transformer 3, after digitlization, the SV nets through intelligent substation send protective chamber device measure and control device 18 to, And then send the MMS nets of the intelligent station to.
When carrying out basic data check to measure and control device at the scene, by the jaw type electricity of interval measurement device 4 in switch yard Flow measurement loop Ia, Ib, Ic, In are connected to the secondary of the conventional current transformer 3 of the behind of combining unit 2 in Intelligent control cabinet On side, voltage measurement circuit Ua, Ub, Uc, Un of interval measurement device 4 are connected directly between to the conventional voltage after combining unit 2 The secondary side of transformer 1.
Interval measurement device 4 by the first electric current card stream clamp the 11, second electric current card stream clamp the 12, the 3rd electric current card stream pincers 13, Neutral current card stream pincers 10 come measure respectively the string branch road conventional current transformer 3 secondary side A phase, B phase, C phase and in The electric current of the inflow combining unit 2 of property line;Pass through first voltage line 14, second voltage line 15, tertiary voltage line 16, neutral conductor electricity Line ball 17 closes to measure the secondary side A phase, B phase, C phase of conventional voltage transformer 1 for accessing the string branch road and neutral conductor access respectively And the voltage of unit 2, and then active, the idle and its direction that the string branch road is flowed to from bus is measured in real time, while being defended by GPS The moment of star sync cap 28 monitors the numerical value of clock, and at this moment idle is preserved when the gps satellite time is integer minute Power is sent with power direction and to measurement head station 5.
Interval measurement device 4 is after the reactive power of the string branch road and direction is measured, through WLAN WLAN interface 7 Send to head station WLAN interface 8, and then arrive measurement head station 5;MMS interface 19 of the head station 5 through MMS Ethernet adaptation modules is measured, Voltage, the electricity that protective chamber device measure and control device 18 is published in this online interval of MMS are obtained on the net from intelligent substation MMS The electric parameters such as stream.Handled after reception after data in its internal list and be shown in measurement head station display panel 9.
The structure of interval measurement device on other branch roads, interval measurement device and conventional current transformer, conventional voltage The connected mode of the secondary circuit of transformer, and the work that interval measurement device is verified to the data on the string branch road are former Reason, it is identical with the branch road, repeat no more here.
In the present embodiment, by the wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer, school is carried out The method tested comprises the following steps:
The first step:Interval measurement device 4 is clamped into the 11, second electric current card stream by the first electric current card stream and clamps the 12, the 3rd electric current Block stream pincers 13, neutral current card stream the pincers 10 outer A phase secondary sides wiring outside for being stuck in conventional current transformer, B phases two respectively On the outside of secondary side joint line, on the outside of the wiring of C phase secondary sides, on the outside of the wiring of the secondary side neutral conductor;
By current measurement A/D module 26, the stream of conventional current transformer secondary side A phase, B phase, C phase and the neutral conductor is measured Enter the electric current of the first string combining unit 2;
By the first voltage line 14 of interval measurement device 4, second voltage line 15, tertiary voltage line 16, neutral conductor pressure-wire The 17 A phase secondary sides wiring for being connected to conventional voltage transformer, the wiring of B phase secondary sides, the wiring of C phase secondary sides, the neutral conductor In secondary side wiring;
By voltage measurement A/D module 25, connecing for conventional voltage transformer secondary side A phase, B phase, C phase and the neutral conductor is measured Enter the voltage of the first string combining unit 2;
And then active, the idle and its direction that the string branch road is flowed to from bus is measured in real time, while synchronous by gps satellite The moment of interface 6 monitors the numerical value of clock.
Second step:Interval measurement device 4 receives the clock signal of synchronous satellite by gps satellite sync cap 6 thereon, And under the preservation of whole time the electric current at the branch road interval, active, idle and its direction.Interval measurement device 4 props up this The electric current at road interval, active, idle and its direction, the time tag for adding this moment is packaged into packet together, by nothing Line LAN WLAN interface 7 is sent to the measurement head station 5 equipped with head station WLAN interface 8.
Interval measurement device and conventional current transformer, the company of the secondary circuit of conventional voltage transformer on other branch roads Mode, and the operation principle that interval measurement device is verified to the data on the string branch road are connect, it is identical with the branch road, here Repeat no more.
3rd step:Measurement head station 5 is linked into the MMS of 3/2 part of intelligent substation nets, and the moment carries from the net Take be sent on each measure and control device station level by active, the idle and its direction in observing and controlling branch road interval, and netted by MMS Pair when signal record monitor clock signal in real time, and be stored in inside measurement head station 5.
4th step:Measurement head station 5 receive each interval measurement device pass through WLAN WLAN interface send each Behind the electric current at branch road interval, active, idle and its direction, it will be sorted according to branch road compartment name, and represent connect from WLAN respectively Mouthful time tag is sent, taken the time of measuring of same whole time, electric current, active, idle and its direction and from MMS nets The time of measuring that arrives, electric current, active, idle list respectively, and calculate whole piece bus and active power and and reactive power.
5th step:Measurement head station 5 shows the key parameter of previous step on its measurement head station display panel 9.
The data of display are as follows:
Table 1
As can be seen from the above table, the reactive power of whole piece bus is balance, but from the point of view of the data that MMS is got on the net, The idle of whole piece bus is in unbalanced state, and the idle data of branch road 1 and branch road 4 have problem.
Embodiment of above is merely to illustrate the present invention, rather than limitation of the present invention.Although with reference to embodiment to this hair It is bright to be described in detail, it will be understood by those within the art that, to technical scheme carry out it is various combination, Modification or equivalent, without departure from the spirit and scope of technical solution of the present invention, the right that all should cover in the present invention is wanted Ask among scope.

Claims (2)

1. a kind of wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer, it is characterised in that including one Above interval measurement device (4);
Interval measurement device (4) the connection electric current card stream pincers and pressure-wire, pass through the merging in Intelligent control cabinet in transformer station Unit (2) connection conventional current transformer (3), the secondary circuit of conventional voltage transformer (1);
The interval measurement device (4) is made up of a set of modular equipment being arranged in a complete enclosure, bag The first CPU module (20) is included, the first chargeable electrical storage device (21), the first power supply are provided with the periphery of the first CPU module (20) Button switch (22), the first clock module (23), the first watchdog module (24), the electricity for connecting three-phase voltage measurement loop Pressure measurement A/D module (25), the current measurement A/D module (26) for connecting three-phase current measuring loop, the first WLAN adaptation moulds Block (27), gps satellite synchronous interface module (28), the first memory module (29), indicating lamp module (30);
The voltage measurement A/D module (25) has voltage measurement circuit Ua, Ub, Uc, Un;
The current measurement A/D module (26) has jaw type current measurement circuit Ia, Ib, Ic, In;
Interval measurement device (4) clamps the secondary side joint of A phases that conventional current transformer (3) is stuck in outside (11) by the first electric current card stream On the outside of line, to measure input jaw type current measurement circuit Ia current value, so that obtaining secondary side A phases flows into combining unit (2) electric current;Clamped and be stuck in outside (12) on the outside of the B phase secondary sides wiring of conventional current transformer (3) by the second electric current card stream, come Input jaw type current measurement circuit Ib current value is measured, so as to obtain the electric current that secondary side B phases flow into combining unit (2); Clamped and be stuck in outside (13) on the outside of the C phase secondary sides wiring of conventional current transformer (3) by the 3rd electric current card stream, to measure input Jaw type current measurement circuit Ic current value, so as to obtain the electric current that secondary side C phases flow into combining unit (2);Pass through the neutral conductor On the outside of the secondary side neutral conductor wiring that conventional current transformer (3) is stuck in outside electric current card stream pincers (10), to measure input jaw type Current measurement circuit In current value, so as to obtain the electric current that the secondary side neutral conductor flows into combining unit (2);
Interval measurement device (4) is connected directly between the secondary side joint of A phases of conventional voltage transformer (1) by first voltage line (14) On line, for measuring voltage measurement circuit Ua voltage, so as to obtain the voltage that secondary side A phases access combining unit (2);Pass through Second voltage line (15) is connected directly between in the B phase secondary side wiring of conventional voltage transformer (1), is returned for measuring voltage measurement Road Ub voltage, so as to obtain the voltage that secondary side B phases access combining unit (2);It is directly connected to by tertiary voltage line (16) In the C phase secondary side wiring of conventional voltage transformer (1), for measuring voltage measurement circuit Uc voltage, so as to obtain two Secondary side C phases access the voltage of combining unit (2);Conventional voltage transformer (1) is connected directly between by neutral conductor pressure-wire (17) Neutral conductor secondary side wiring on, for measuring voltage measurement circuit Un voltage, thus obtain the secondary side neutral conductor access conjunction And the voltage of unit (2);
Interval measurement device (4) obtains synchronous by the gps satellite sync cap (6) on gps satellite synchronous interface module (28) Time, by the WLAN WLAN interface (7) in the first WLAN adaptation modules (27) to equipped with head station WLAN interface (8) Measurement head station (5) sends time and the electric parameter that interval measurement device (4) is measured;
What the measurement head station (5) was made up of a set of modular equipment being arranged in a complete enclosure, including second CPU module (31), the periphery of second CPU module (31) is provided with the second chargeable electrical storage device (32), second source button Switch (33), second clock module (34), the second watchdog module (35), the 2nd WLAN adaptation modules (36), the second storage mould Block (37), MMS Ethernets adaptation module (38);
Head station (5) is measured to receive from interval measurement device by the WLAN interface (8) of the WLAN adaptation modules (36) of head station the 2nd (4) data sent through WLAN WLAN interface (7).
2. the intelligent station 3/2 wiring bus reactive power rate tester according to claim 1 based on traditional transformer, it is special Levy and be, traditional wiring bus tester of transformer intelligent transformer station 3/2 includes four interval measurement devices.
CN201410262275.2A 2014-06-12 2014-06-12 The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer Active CN105203984B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410262275.2A CN105203984B (en) 2014-06-12 2014-06-12 The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410262275.2A CN105203984B (en) 2014-06-12 2014-06-12 The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer

Publications (2)

Publication Number Publication Date
CN105203984A CN105203984A (en) 2015-12-30
CN105203984B true CN105203984B (en) 2017-07-18

Family

ID=54951764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410262275.2A Active CN105203984B (en) 2014-06-12 2014-06-12 The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer

Country Status (1)

Country Link
CN (1) CN105203984B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105655879B (en) * 2016-01-19 2018-05-04 国网福建省电力有限公司泉州供电公司 The voltage arrangement of 110 kilovolts of system busbar combining unit duplicate system retrofits of intelligent substation double bus scheme mode

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6496342B1 (en) * 1999-02-12 2002-12-17 Bitronics Inc. Distributed monitoring and protection system for a distributed power network
CN101498775A (en) * 2009-03-17 2009-08-05 江苏省电力试验研究院有限公司 Calibration apparatus for gate energy meter of digitized transforming plant
CN201444193U (en) * 2009-05-27 2010-04-28 辽宁省电力有限公司鞍山供电公司 Comprehensive error detection device used for digital electric energy measuring device
CN102156274A (en) * 2011-04-22 2011-08-17 四川电力科学研究院 Field integral detecting system of three-phase electric energy measuring system of electric distribution network
CN102608450A (en) * 2012-02-24 2012-07-25 江苏凌创电气自动化股份有限公司 Testing and verifying system appropriate for intelligent transformer substation and verifying method
CN202583449U (en) * 2012-05-31 2012-12-05 江西省电力科学研究院 Whole detection device of intelligent transformer station electric energy metering device
KR20120137615A (en) * 2011-05-26 2012-12-24 한국전력공사 System for substation automation, method for obtaining surveillance data of substation
CN202758062U (en) * 2012-07-05 2013-02-27 广东电网公司电力科学研究院 Overall metering error detection system of digital transformer station electric energy metering device
CN103018709A (en) * 2012-12-18 2013-04-03 广东电网公司潮州供电局 Method and system for monitoring error of gateway metering device
CN202886584U (en) * 2012-09-14 2013-04-17 珠海威瀚科技发展有限公司 Novel integrated error checking device of high-voltage energy measurement device
CN103094986A (en) * 2013-02-20 2013-05-08 湖南省电力公司科学研究院 Distributed detection method of intelligent substation relay protection devices based on digital dynamic real time simulator (DDRTS)
JP5433115B1 (en) * 2013-05-21 2014-03-05 三菱電機株式会社 Process bus protection control system, merging unit and arithmetic unit
CN103630868A (en) * 2013-09-23 2014-03-12 中国电子科技集团公司第二十七研究所 Remote substation electrical energy metering information detection system
CN203554071U (en) * 2013-11-01 2014-04-16 北京博电新力电气股份有限公司 Intelligent transformer station merging unit automatic verification device
CN103823199A (en) * 2014-03-03 2014-05-28 国家电网公司 Automatic detection system and detection method for intelligent substation relay protection testing device
CN204009048U (en) * 2014-06-12 2014-12-10 国网山西省电力公司电力科学研究院 Intelligent station 3/2 wiring bus reactive power tester based on traditional mutual inductor

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6496342B1 (en) * 1999-02-12 2002-12-17 Bitronics Inc. Distributed monitoring and protection system for a distributed power network
CN101498775A (en) * 2009-03-17 2009-08-05 江苏省电力试验研究院有限公司 Calibration apparatus for gate energy meter of digitized transforming plant
CN201444193U (en) * 2009-05-27 2010-04-28 辽宁省电力有限公司鞍山供电公司 Comprehensive error detection device used for digital electric energy measuring device
CN102156274A (en) * 2011-04-22 2011-08-17 四川电力科学研究院 Field integral detecting system of three-phase electric energy measuring system of electric distribution network
KR20120137615A (en) * 2011-05-26 2012-12-24 한국전력공사 System for substation automation, method for obtaining surveillance data of substation
CN102608450A (en) * 2012-02-24 2012-07-25 江苏凌创电气自动化股份有限公司 Testing and verifying system appropriate for intelligent transformer substation and verifying method
CN202583449U (en) * 2012-05-31 2012-12-05 江西省电力科学研究院 Whole detection device of intelligent transformer station electric energy metering device
CN202758062U (en) * 2012-07-05 2013-02-27 广东电网公司电力科学研究院 Overall metering error detection system of digital transformer station electric energy metering device
CN202886584U (en) * 2012-09-14 2013-04-17 珠海威瀚科技发展有限公司 Novel integrated error checking device of high-voltage energy measurement device
CN103018709A (en) * 2012-12-18 2013-04-03 广东电网公司潮州供电局 Method and system for monitoring error of gateway metering device
CN103094986A (en) * 2013-02-20 2013-05-08 湖南省电力公司科学研究院 Distributed detection method of intelligent substation relay protection devices based on digital dynamic real time simulator (DDRTS)
JP5433115B1 (en) * 2013-05-21 2014-03-05 三菱電機株式会社 Process bus protection control system, merging unit and arithmetic unit
CN103630868A (en) * 2013-09-23 2014-03-12 中国电子科技集团公司第二十七研究所 Remote substation electrical energy metering information detection system
CN203554071U (en) * 2013-11-01 2014-04-16 北京博电新力电气股份有限公司 Intelligent transformer station merging unit automatic verification device
CN103823199A (en) * 2014-03-03 2014-05-28 国家电网公司 Automatic detection system and detection method for intelligent substation relay protection testing device
CN204009048U (en) * 2014-06-12 2014-12-10 国网山西省电力公司电力科学研究院 Intelligent station 3/2 wiring bus reactive power tester based on traditional mutual inductor

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
数字化变电站继电保护闭环实时仿真系统研究;孟恒信等;《电网技术》;20101231;第 34 卷(第 12 期);198-203页 *
智能变电站交流实时测量功能试验方法;陈宏;《湖北电力》;20140430;第38卷(第4期);27-32页 *
智能变电站合并单元智能终端集成技术探讨;倪益民等;《电力系统自动化》;20140625;第38卷(第12期);95-99页 *

Also Published As

Publication number Publication date
CN105203984A (en) 2015-12-30

Similar Documents

Publication Publication Date Title
CN102621514B (en) Electronic transformer verifying device
CN109143143A (en) Transformer substation current transformer secondary side polarity intelligent detection device and method
CN105260840B (en) A kind of internet+schedulable load synthesis scheduling system
CN107945608A (en) Almightiness type power supply station Training in Comprehensive Skills device
CN102129061A (en) Automatic wiring detection device and method for three-phase simulation electric energy meter
Gallo et al. Low cost smart power metering
CN109582004A (en) Intelligent measurement platform
CN105388385A (en) Bus differential protection vector concentrated test method
CN203630193U (en) Low-voltage current measuring rod
CN105203984B (en) The wiring bus reactive power rate tester of intelligent station 3/2 based on traditional transformer
CN105319436B (en) The wiring bus reactive power rate method of calibration of intelligent station 3/2 based on traditional transformer
CN202057747U (en) Intelligent secondary circuit vector analyzer
CN104076197A (en) Unbalanced current testing device and method for capacitor bank
CN204009048U (en) Intelligent station 3/2 wiring bus reactive power tester based on traditional mutual inductor
CN105891602B (en) A kind of earthing or grounding means GPS shunting phase shift test method and system
CN102508052B (en) Test method for field band channel operation of automatic bus transfer system of area network
CN204945366U (en) A kind of wirelessly transmitting electrical energy metering on-site calibration device
CN106526319A (en) Synchronous phase measurement method and system
CN105044517B (en) Intelligent substation based on tidal characteristics value protects vector analysis method
CN208271415U (en) Almightiness type power supply station Training in Comprehensive Skills device
CN105589011A (en) Missort investigation device and investigation method before installation of single-phase resident ammeter
CN207472993U (en) A kind of electric energy quality detection device with electric fire disaster warning function
CN209373090U (en) The on-line monitoring system of voltage transformer secondary voltage drop
CN203645395U (en) Quick external power box for power utilization of substation
CN203479897U (en) Dual-channel metering single-phase electric energy meter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Li Rui

Inventor after: Kang Yinzhu

Inventor after: Song Shuyong

Inventor after: Ma Zhenguo

Inventor after: Hao Wei

Inventor after: Sun Ruihao

Inventor after: Zhang Yue

Inventor after: Liu Jie

Inventor before: Li Rui

Inventor before: Song Shuyong

Inventor before: Ma Zhenguo

Inventor before: Hao Wei

Inventor before: Sun Ruihao

Inventor before: Zhang Yue

Inventor before: Liu Jie